What is test first development?

  1. The continuous restructuring of software to retain flexibility
  2. Having the tester in the development team write the test plans before coding
  3. Creating tests before satisfying them
  4. Testing existing code before adding more code to it

Answer(s): B

Explanation:

Test first development is a different way of saying TDD.



How do you know that the developers are cross-functional?

  1. Every member can do every task
  2. They work with TDD
  3. They never argue
  4. They do pair programming
  5. Developers have the combined skills to create a usable increment

Answer(s): E

Explanation:

Cross-functional is on team level and not on individual level.



The practice of decomposing a requirement into failing tests is called:

  1. Behavior driven development
  2. Scrum testing
  3. Regression testing
  4. Acceptance test driven development

Answer(s): D

Explanation:

In ATDD you start with writing tests to represent the requirement. Since you start with this, there is no production code to satisfy the test which is why the tests will fail.



Scrum demands code review

  1. True
  2. False

Answer(s): B

Explanation:

There are no concrete development guidelines demanded by scrum, even though code review is an excellent idea. Scrum is also not only about developing software.



What are three of the best ways to address non-functional requirements?

  1. Handle them during a risk mitigation phase before development
  2. Scrum is for functional, frontend development only
  3. Include them in the Product Backlog
  4. Before the release, they should be tested and validated in a hardening sprint
  5. Specific expectations can be used as acceptance criteria to specific product backlog items
  6. Important, recurring non-functional requirements can be added to the definition of done

Answer(s): A,E,F

Explanation:

There is no hardening sprint, there are only regular sprints. If it's an ever recurring non-functional requirement, it can be added to the definition of done. If it's not it can be added (as a criteria) in the product backlog (item).