You have six teams using a traditional method to deliver a product. Your management has asked you to start using Scrum. In the initial project there were separate plans and teams for the layers of a software system, i.e. one for the front-end, one for the middle tier, one for the back-end, and one for the interfaces and services. This resembles what is known as component teams. But you have read that it’s a good idea to have teams organized by feature.

What are the advantages of keeping component teams while starting Scrum?

  1. There’s less initial disruption than organizing into new teams. As they start, they will discover what works best, and how to potentially re-organize towards this.
  2. Component teams generally have the skills needed to create a working Increment of software that provides business value.
  3. Because they have worked together for some time, they are likely able to start producing shippable Increments faster that new feature teams would.
  4. There are fewer cross-team dependencies than working in feature teams.

Answer(s): A



How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

  1. The Scrum Team with the highest velocity pulls Product Backlog items first.
  2. The Development Teams pull in work in agreement with the Product Owner.
  3. The Product Owner should provide each team with its own Product Backlog.
  4. Each Scrum Team takes an equal numbers of items.
  5. The Product Owner decides.

Answer(s): B



How often should Development Team membership change?

  1. As needed, while taking into account a short term reduction in productivity.
  2. Never, because it reduces productivity.
  3. As needed, with no special allowance for changes in productivity.
  4. Every Sprint to promote shared learning.

Answer(s): A



Who should make sure everyone on the Development Team does his or her tasks for the Sprint?

  1. The Project Manager.
  2. The Product Owner.
  3. The Scrum Master.
  4. The Development Team.
  5. All of the above.

Answer(s): D


Reference:

https://backlog.com/blog/quick-guide-scrum-roles-responsibilities/






Post your Comments and Discuss Scrum PSM I exam with other Community members:

Bianca commented on November 13, 2024
Consistent questions
Anonymous
upvote

govind commented on September 01, 2024
nice questions
Anonymous
upvote

Narendra Kumar commented on August 21, 2024
Nice questions
Anonymous
upvote

Charls commented on August 18, 2024
I managed to pass this exam but only with the use of this exam dumps.
Spain
upvote

Nilam commented on August 18, 2024
This was a difficult but I passed it. Got very happy with my result.
INDIA
upvote

Govind commented on August 15, 2024
Going to appear for the exam
Anonymous
upvote

Suchita Dange commented on July 29, 2024
Thanks for your support to prepare for exam,
AUSTRALIA
upvote

Khandaker Mahamud Riyadh commented on June 13, 2024
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information: Sprint 1: 10 pontos - Sprint 2: 11 pontos - Sprint 3: 15 pontos - Sprint 4: 14 pontos - Sprint 5: 15 pontos - Sprint 6: 10 pontos - The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development? A. 6 B. 5 C. 4 D. 3 What would be correct answer? I think (C)
Anonymous
upvote

Khandaker Mahamud Riyadh commented on June 13, 2024
I really love to answer. Thanks.
Anonymous
upvote

ossama charaf commented on April 14, 2024
good experiences
BELGIUM
upvote

PSM Prospect commented on March 22, 2024
I agree with Minja on Question 107. The Developers are self-managed and should be responsible for removing the impediment, with help from the Scrum Master. There is no such thing as a Scrum Manager role in Scrum. The Scrum Master is there to guide the development team and also remove impediments discovered by the development team.
Anonymous
upvote

PSM Prospect commented on March 22, 2024
This is to Anonymous (Poster at 3/21/2024 - 6:00:08PM) Answer to Question 110 is correct - D. If you read the scrum guide, the purpose of the Sprint Review is to inspect the Sprint outcome and figure out future adaptations.
Anonymous
upvote

Anonymous commented on March 21, 2024
Answer on question 110 is wrong - it should be B It is a demo at the end of the Sprint for everyone in the organization to check on the work done.
UNITED STATES
upvote

PSM Prospect commented on March 21, 2024
Answer on question 11 is wrong - only Sprint Retrospective is required.
Anonymous
upvote

Sam commented on March 20, 2024
very helpful
UNITED STATES
upvote

Anne commented on March 17, 2024
just started, I need to work more on them to understand, thanks anyway.
Anonymous
upvote

Simon commented on February 14, 2024
Best solution to pass this exam. You can call it cheating but that is the only way to pass this exam. The PDF version is well formatted and easy to use.
Mexico
upvote

Armo commented on February 12, 2024
very helpful
UKRAINE
upvote

Prateek commented on January 30, 2024
Very Helpful
Anonymous
upvote

Chandra commented on January 24, 2024
Very helpful
Anonymous
upvote

Umashankar Sharma commented on October 22, 2023
planning to take psm test
Anonymous
upvote

Aderonke commented on October 23, 2023
helpful assessment
UNITED KINGDOM
upvote

Aderonke commented on October 31, 2023
fantastic assessments
Anonymous
upvote

Krishneel commented on March 17, 2023
i just passed. this exam dumps is the same one from prepaway and examcollection. it has all the real test questions.
INDIA
upvote

Rajender commented on October 18, 2023
i would like to take psm1 exam.
Anonymous
upvote

Aderonke commented on October 23, 2023
fantastic assessment on psm 1
UNITED KINGDOM
upvote

Aderonke commented on October 23, 2023
very helpful assessments
UNITED KINGDOM
upvote

Roberto Capra commented on June 14, 2023
nice questions... are these questions the same of the exam?
Anonymous
upvote

Aderonke commented on October 23, 2023
brilliant and helpful
UNITED KINGDOM
upvote

francesco commented on October 30, 2023
helpful on 2017 scrum guide
EUROPEAN UNION
upvote

vinay commented on September 04, 2023
really nice
Anonymous
upvote

Ashwini commented on August 22, 2023
it really helped
Anonymous
upvote

Jude commented on August 29, 2023
why is the answer to "which of the following is required by scrum?" all of the following stated below since most of them are not mandatory? sprint retrospective. members must be stand up at the daily scrum. sprint burndown chart. release planning.
UNITED STATES
upvote

D commented on January 03, 2024
Answer (All of the above) for Question #11 is wrong. Only Sprint Retrospective is required by Scrum - all the others even do not exist as mandatory parts.
Anonymous
upvote