Scrum PSM I Exam Questions
Professional Scrum Master I (Page 4 )

Updated On: 21-Feb-2026

Which of the following is required by Scrum? (Choose all that apply.)

  1. Sprint Retrospective.
  2. Members must be stand up at the Daily Scrum.
  3. Sprint Burndown Chart.
  4. Release planning.
  5. All of the above.

Answer(s): A,D

Explanation:

Explanation of

Answer(s): According to the Scrum Guide1, the only required events in Scrum are Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. These events enable transparency, inspection, and adaptation. The other options are not mandatory in Scrum, although they may be useful in some contexts.


Reference:

Scrum Guide



What is the purpose of a Sprint Review?

  1. To take time to judge the validity of the project.
  2. To inspect the product increment with the stakeholders and collect feedback on next steps.
  3. To review the Scrum Team's activities and processes during the Sprint.
  4. To build team sprint.

Answer(s): B



Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

  1. The Scrum Team.
  2. The Product Owner.
  3. The Developers.
  4. The Project Manager.

Answer(s): C



Who must attend the Daily Scrum?

  1. The Scrum Master and Product Owner.
  2. The Development Team.
  3. The Development Team and Product Owner.
  4. The Scrum Team.
  5. The Development Team and Scrum Master.

Answer(s): D

Explanation:

According to the Scrum Guide1, the Daily Scrum is an event for the Developers of the Scrum Team. The purpose of the Daily Scrum is to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work. The Scrum Master and Product Owner may attend as observers, but only if it is useful for the Developers.


Reference:

Scrum Guide



When do Development Team members take ownership of a Sprint Backlog item?

  1. At the Sprint planning meeting.
  2. During the Daily Scrum.
  3. Never. All Sprint Backlog Items are "owned" by the entire Development Team, even though each one may be done by an individual Development Team member.
  4. Whenever a team member can accommodate more work.

Answer(s): C

Explanation:

According to the Scrum Guide1, the Sprint Backlog is the property of the Developers and no one else can tell them which items they should work on. The Developers can select any item from the Product Backlog that they forecast they can complete within a Sprint. The Developers are self-organizing and decide how to turn Product Backlog items into an Increment of value. Therefore, no one owns a Sprint Backlog item, but the entire Development Team is accountable for it.


Reference:

Scrum Guide






Post your Comments and Discuss Scrum PSM I exam dumps with other Community members:

Join the PSM I Discussion