Free PSPO-I Exam Braindumps (page: 21)

Page 21 of 43

Who starts the Daily Scrum?
(choose the best answer)

  1. The Scrum Master. This ensures that the Developers have the event, and it stays within the timebox.
  2. The person coming in last. This encourages people to be on time and helps to stay within the timebox.
  3. The Product Owner.
  4. Whoever the Developers decide should start.
  5. The person who has the token.

Answer(s): D

Explanation:

The Daily Scrum is an event for and by the Developers. They can choose whatever structure and technique they want, as long as they focus on the progress toward the Sprint Goal and produce an actionable plan for the next day of work12. The Scrum Master, the Product Owner, and the person coming in last are not necessarily the ones who should start the Daily Scrum. The person who has the token is a possible technique, but not the only one3.



When does a Sprint conclude?
(choose the best answer)

  1. When all the tasks are completed by the Developers.
  2. When the Sprint Retrospective is complete.
  3. When all Product Backlog items meet their Definition of Done.
  4. When the Product Owner decides enough has been delivered to meet the Sprint Goal.

Answer(s): D

Explanation:

A Sprint is a time-boxed period when a Scrum Team works to complete a set amount of work that delivers value to the customer1. A Sprint concludes when the time-box expires, regardless of whether all the tasks, Product Backlog items, or Definition of Done are completed or not23. The Product Owner has the authority to cancel a Sprint if they determine that the Sprint Goal is obsolete or the work done is no longer valuable1. Therefore, the Product Owner decides when enough has been delivered to meet the Sprint Goal, and the Sprint ends accordingly.



Which topics should be discussed in the Sprint Review? (choose the best answer)

  1. The Scrum process, and how it was used during the Sprint.
  2. Coding and engineering practices.
  3. The product Increment.
  4. All of the above.

Answer(s): C

Explanation:

The main topic of discussion is the product Increment, which is the sum of all the Product Backlog items completed during a Sprint and the value of the increments of all previous Sprints1. The product Increment is demonstrated and inspected by the attendees, and feedback is collected to inform the next Sprint Planning12. The Sprint Review may also include other topics, such as the Product Backlog, the Product Goal, the market conditions, the budget, and the timeline, but the product Increment is the essential topic1234. The Scrum process, and how it was used during the Sprint, is not a topic for the Sprint Review, but rather for the Sprint Retrospective, which is a separate event where the Scrum Team inspects and adapts its way of working1. Coding and engineering practices are also not relevant for the Sprint Review, as they are internal aspects of the Development Team that do not affect the value of the product Increment1. Therefore, the correct answer is C. The product Increment.



Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item?

(choose the best two answers)

  1. Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.
  2. Refocus the current Sprint on establishing the Scrum Team's environment instead of delivering an Increment.
  3. Encourage the Product Owner to accept partially done Increments until the situation improves.
  4. Have the Scrum Team establish a Definition of Done that is actually possible to achieve given current circumstances.
  5. Declare the Scrum Team not ready for Scrum.

Answer(s): A,D

Explanation:



Explore
The correct answers are A and D)
A) Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly. This is an appropriate action for a Scrum Master, as it helps the Scrum Team to overcome the impediments that prevent them from delivering a potentially releasable Increment. The Definition of Done should reflect the current reality of the Scrum Team, but also be a source of continuous improvement12.
D) Have the Scrum Team establish a Definition of Done that is actually possible to achieve given current circumstances. This is also an appropriate action for a Scrum Master, as it ensures that the Scrum Team has a clear and shared understanding of what it means to complete a Product Backlog item. The Definition of Done should be realistic and achievable, but also challenging and ambitious12.
B) Refocus the current Sprint on establishing the Scrum Team's environment instead of delivering an Increment. This is not an appropriate action for a Scrum Master, as it violates the purpose of the Sprint, which is to deliver a valuable product Increment that meets the Sprint Goal. The Scrum Team should not change the Sprint Goal or scope during the Sprint, unless the Product Owner decides to cancel the Sprint3.
C) Encourage the Product Owner to accept partially done Increments until the situation improves. This is not an appropriate action for a Scrum Master, as it compromises the quality and value of the product. The Product Owner should only accept Increments that meet the Definition of Done and the acceptance criteria. Partially done Increments increase technical debt and risk, and reduce transparency and feedback12.
E) Declare the Scrum Team not ready for Scrum. This is not an appropriate action for a Scrum Master, as it undermines the Scrum values and principles. The Scrum Master should support the Scrum Team in adopting and applying Scrum, regardless of the challenges and constraints they face. The Scrum Master should foster a culture of empiricism, self-organization, collaboration, and continuous improvement.



Page 21 of 43



Post your Comments and Discuss Scrum PSPO-I exam with other Community members:

Barbara commented on October 07, 2024
good content!
UNITED STATES
upvote