What happens if the Scrum Team cannot complete its work by the end of the Sprint? (choose the best answer)
Answer(s): A
If the Scrum Team cannot complete its work by the end of the Sprint, the Sprint does not get extended. Instead, the unfinished Sprint Backlog Items go back to the Product Backlog and can be addressed in the following Sprint12. This approach allows the team to get better at estimating and reduces complexity due to the consistency of the Scrum Events2. The Scrum Team continuously learns and adapts12.
True or False: Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.
When does the next Sprint begin?(choose the best answer)
Answer(s): B
What are the two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity?(choose the best two answers)
Answer(s): B,D
The two primary ways a Scrum Master helps a Scrum Team work at its highest level of productivity are by facilitating Scrum Team decisions and by removing impediments that hinder the Scrum Team12. The Scrum Master is a facilitator and a coach, helping the team remove impediments and facilitating team decisions12. This enables the team to focus on their work and maintain their productivity12.
Post your Comments and Discuss Scrum PSPO-I exam with other Community members:
Barbara commented on October 07, 2024 good content! UNITED STATES upvote
Our website is free, but we have to fight against bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the PSPO-I content, but please register or login to continue.