The Architecture Vision phase of a TOGAF ADM cycle is intended to achieve all of the following objectives except .

  1. Defining key business requirements to be achieved
  2. Verification of relevant principles, business goals, and objectives
  3. Defining relevant stakeholders
  4. Define the framework and core architecture principles that will govern future architecture work
  5. Articulating an architecture vision

Answer(s): D



Which of the following statements is most true?

  1. Architecture principles have the highest precedence in the hierarchy of principles
  2. Each project should define its own set of principles
  3. In a federated organization, each individual unit may need to define some principles that are unique.
  4. In a federated organization, each individual unit must, of necessity, be fully conformant to the federation's principles
  5. Architecture principles are generic, and can be shared between organizations without modification

Answer(s): C



What is the scope of a super-domain architecture as described in TOGAF?

  1. A super-domain canspan horizontally across multiple organizational units.
  2. A conglomerate enterprise architecture that spans multiple enterprises.
  3. A detailed vertical architecture that focuses on the implementation of a specific infrastructure service.
  4. It is a high level "meta architecture" that encapsulates the other domains.
  5. none of these

Answer(s): A



When identifying project constraints, which of the following is not true?

  1. TOGAF allows project architects to set aside principles that they believe would interfere with the project as long as the decision to do so is explictly documented
  2. Enterprise wide constraints are often derived from the organization's business and architecture principles
  3. Project specific constraints should not supercede enterprise wide constraints.
  4. Specific technology solutions are not considered constraints when formulating the architecture vision.
  5. Time, schedule, and resource availability are considered project constraints when formulating the architecture vision.

Answer(s): A



In the Architecture Vision phase, it is important to capture the concerns of the .

  1. Key stakeholders
  2. Top management
  3. Implementation governance board
  4. Regulatory agencies
  5. User community

Answer(s): A