What LEED Building Design and Construction rating system mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit?

  1. Healthcare
  2. Schools
  3. Data centers
  4. Hospitality

Answer(s): C

Explanation:

Data centers is the only LEED BD+C rating system that mandates a preliminary LEED meeting with the principal members of the project team to create a LEED action plan that includes the anticipated certification tier, targeted credits and parties responsible for each credit. This is because data centers have unique design and operational characteristics that require a more integrative and customized approach to achieve LEED certification. The preliminary LEED meeting is intended to facilitate early goal setting, alignment, and communication among the project team members.


Reference:

LEED BD+C Reference Guide, Data Centers, page 91; LEED v4.1 BD+C: Data Centers



Which of these is a method to assess the regional context of a building's design for sustainability?

  1. Conducting a site analysis
  2. Consulting with neighbors
  3. Improving a design threshold
  4. Performing an energy analysis of the building

Answer(s): A

Explanation:

Conducting a site analysis is a method to assess the regional context of a building's design for sustainability. A site analysis involves collecting and evaluating information about the site's location, climate, ecology, history, culture, infrastructure, regulations, and stakeholders. This can help identify the opportunities and constraints for the project, as well as the potential impacts and benefits for the environment and the community. A site analysis can inform the design decisions regarding site selection, site development, water management, energy efficiency, material selection, indoor environmental quality, and innovation.


Reference:

LEED BD+C Reference Guide, Integrative Process, page 281; Site Analysis for Construction



To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate

  1. all luminaires have full cutoff fixtures
  2. all luminaires have a minimum color temperature of 3500 K
  3. all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO)

    lighting zone
  4. all luminaires are mounted at least three mounting heights from the lighting boundary

Answer(s): C

Explanation:

To achieve the Sustainable Sites Credit, Light Pollution Reduction, Option 1. BUG Rating Method, projects must demonstrate that all luminaires meet acceptable fixture ratings for the project's Model Lighting Ordnance (MLO) lighting zone. The MLO lighting zone is determined by the site-specific characteristics and the definitions provided in the IES/IDA MLO User Guide. The fixture ratings are based on the backlight-uplight-glare (BUG) system, which measures the amount of light emitted in different directions by a luminaire, as defined in IES TM-15-11, Addendum A2. The maximum allowable ratings for each lighting zone are given in Table 1 of the credit language.


Reference:

IES/IDA MLO User Guide; IES TM-15-11, Addendum A; Light pollution reduction



A tenant of a new office building will require 100 workstations per floor. Each floor will have two bathroom facilities and one conference room. How many lighting control devices with at least three lighting levels per floor are required to comply with Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control?

  1. 91 lighting control devices
  2. 93 lighting control devices
  3. 100 lighting control devices
  4. 103 lighting control devices

Answer(s): B

Explanation:

To comply with Indoor Environmental Quality Credit, Interior Lighting, Option 1. Lighting Control, the tenant of a new office building will require 93 lighting control devices with at least three lighting levels per floor. This is because the credit requires that at least 90% of individual occupant spaces have lighting controls that enable occupants to adjust the lighting to suit their individual tasks and preferences. The credit also requires that all shared multioccupant spaces have lighting controls that enable adjustments that meet the needs of the group. According to the LEED BD+C Reference Guide, an individual occupant space is defined as an enclosed space or an open space that is occupied by one person and is at least 50 square feet (4.6 square meters) in area. A shared multioccupant space is defined as an enclosed or open space that is occupied by more than one person and is at least 100 square feet (9.3 square meters) in area. Based on the given information, each workstation can be considered as an individual occupant space, and each bathroom facility and conference room can be considered as a shared multioccupant space. Therefore, the number of lighting control devices per floor can be calculated as follows:
For the 100 workstations, 90% of them need lighting controls, which is 90 workstations. Each workstation needs one lighting control device, so the total number of lighting control devices for the workstations is 90.
For the two bathroom facilities, each facility needs one lighting control device, so the total number of lighting control devices for the bathroom facilities is 2. For the one conference room, one lighting control device is needed, so the total number of lighting control devices for the conference room is 1.
The total number of lighting control devices per floor is then 90 + 2 + 1 = 93.


Reference:

Interior lighting



Viewing page 13 of 78
Viewing questions 49 - 52 out of 305 questions



Post your Comments and Discuss US Green Building Council LEED-AP-BD-C exam prep with other Community members:

LEED-AP-BD-C Exam Discussions & Posts