A project's installed water fixtures do not exceed WaterSense maximum levels.
Which compliance path should the LEED AP select under Water Efficiency Prerequisite, Indoor Water Use Reduction, and what type of documentation is required to demonstrate compliance with this path?

  1. Compliance Path 1: Prescriptive Achievement; product cutsheets
  2. Compliance Path 2: Usage-Based Calculation; indoor water use calculations
  3. Compliance Path 1: Prescriptive Achievement; indoor water use calculations
  4. Compliance Path 2. Usage-Based Calculation; prescriptive compliance confirmation

Answer(s): A

Explanation:

When a project's installed water fixtures do not exceed WaterSense maximum levels, the appropriate compliance path under the Water Efficiency Prerequisite for Indoor Water Use Reduction is Compliance Path 1: Prescriptive Achievement. This path requires product cutsheets as documentation to demonstrate compliance. The product cutsheets serve as verification that the installed fixtures meet the WaterSense labeling requirements and do not exceed the maximum flow rates established by WaterSense standards.


Reference:

The LEED v4 reference guide for Interior Design and Construction outlines the requirements for the Water Efficiency Prerequisite, Indoor Water Use Reduction, including the need for product cutsheets to document compliance with WaterSense maximum levels.



Which of the following prerequisites or credits is affected by using plug-in devices when attempting to achieve Indoor Environmental Quality Credit, Thermal Comfort?

  1. Energy and Atmosphere Credit, Demand Response
  2. Energy and Atmosphere Credit, Advanced Energy Metering
  3. Energy and Atmosphere Prerequisite, Minimum Energy Performance
  4. Energy and Atmosphere Prerequisite, Building Level Energy Metering

Answer(s): C

Explanation:

The use of plug-in devices can affect the Energy and Atmosphere Prerequisite, Minimum Energy Performance, as this prerequisite requires the establishment of a building's energy performance that includes the energy consumption of all plug-in devices. These devices can significantly impact the overall energy usage and therefore influence the strategies to meet the minimum energy performance standards.


Reference:

LEED v4 for Interior Design and Construction Reference Guide.
LEED Credit Library - Energy and Atmosphere.
Minimum Energy Performance Prerequisite Information.

The use of plug-in devices can have a significant impact on a building's energy profile, especially when considering the Indoor Environmental Quality Credit for Thermal Comfort within the LEED AP Interior Design + Construction framework. The Energy and Atmosphere Prerequisite, Minimum

Energy Performance, is affected by the use of plug-in devices because these devices contribute to the building's overall energy consumption. This prerequisite requires projects to establish a minimum level of energy efficiency for the proposed building and systems. Plug-in devices can alter the thermal load and energy usage patterns within a space, thereby influencing the strategies employed to meet thermal comfort requirements. For instance, excessive use of personal heating or cooling devices might indicate inadequacies in the HVAC system's ability to provide comfortable conditions, which could affect the energy modeling and performance metrics required to comply with this prerequisite. It's crucial for the design team to account for the energy impact of plug-in devices in their energy modeling and ensure that the building's systems can meet occupants' thermal comfort needs efficiently.



Which systems must be commissioned to earn Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification?

  1. Fire suppression
  2. Irrigation controls
  3. Building Envelope
  4. Daylighting controls

Answer(s): C

Explanation:

The Fundamental Commissioning and Verification prerequisite requires commissioning of the building's mechanical, electrical, plumbing, and renewable energy systems and assemblies.
While the building envelope is not typically commissioned, it must be included in the owner's project requirements (OPR) and basis of design (BOD), and its design must be reviewed.


Reference:

The LEED v4.1 reference guide for Interior Design and Construction outlines the scope of commissioning process activities, which includes the requirement for exterior enclosures to be limited to inclusion in the OPR and BOD, as well as the review of the OPR, BOD, and project design.



Based on the results of a six-hour waste stream study, the team for an Interior Design and Construction Retail project plans to provide dedicated areas for four recyclable waste streams:
cardboard, plastic, metal, and paper.
The project is open to the public 10 hours a day, six days a week.
Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?

  1. Take appropriate measures for the safe collection, storage and disposal of batteries
  2. Make a waste stream projection for the entire year based on the six hours of the waste stream study
  3. Make a waste stream projection for the entire week, based on the six hours of the waste stream study
  4. Extend the waste stream study to cover a representative time period of a minimum of 24 hours to identify the top five recyclable waste streams

Answer(s): D

Explanation:

For the Materials and Resources Prerequisite, Storage and Collection of Recyclables, the project team must demonstrate that they can effectively manage and divert waste from landfills. Extending the waste stream study to a minimum of 24 hours will provide a more accurate representation of the waste generated and the recyclable streams. This is essential to identify the top five recyclable waste streams, which is a requirement for this prerequisite.


Reference:

The LEED v4 reference guide for Interior Design and Construction specifies that a waste stream audit must cover a representative time period to accurately identify the project's waste streams. Additionally, the LEEDuser website provides guidance on how to conduct a waste stream audit and the importance of identifying the main types of recyclable waste.