VMware VDCD510 Exam Questions
VMware Certified Advanced Professional - Datacenter DesignExam (Page 5 )

Updated On: 16-Feb-2026

In the project life cycle, the defines the vision.

  1. IT architect
  2. software vendor
  3. business

Answer(s): C

Explanation:

By reviewing the current configuration of a system and mapping the final status of components as described in the vision, the business identifies the gap between the two. A gap state analysis is a review of the items or tasks that are required to progress between the stages. Such an analysis is useful in creating milestone plans, implementation orders, and so on.
Chapter 2, Gathering Information and Spotting the Gaps



A(n) is an item that is taken to be true in the design phases but has not been tested prior to execution.

  1. requirement
  2. constraint
  3. assumption
  4. risk

Answer(s): C

Explanation:

An assumption could impact your design. It is good to ensure that project team and wider business are aware of assumptions and that they are agreed and validated as part of the design consideration process. Chapter 2, Gathering Information and Spotting the Gaps



You are a virtualization consultant working on a DR project. You have proposed a solution that uses SAN replication technology to replicate production virtual machine files. This meets the cold standby requirement. Which of the following could be a design constraint?

  1. The hardware currently being used in the datacenter is out of support.
  2. The company is undecided about the choice of centralized storage to be used in the enterprise.
  3. The company is at the end of year 1 of a 3-year contract for the point-to-point link between Site A and Site B. This link is currently 10 MB.

Answer(s): C

Explanation:

An item from the current state analysis that would restrict or change a design choice is potentially a constraint. Such factors can limit a design and in some cases prevent the realization of a project vision.
Chapter 2, Gathering Information and Spotting the Gaps



You are a technical consultant designing a solution for an online retail company. The project vision is to deploy a hybrid cloud, with the internal team developing the website on internal infrastructure and migrating production-ready applications to a hosting provider. The project is expected to ease deployment and require less infrastructure capital expenditure--without lowering application quality. Which of the following is a risk to the project?

  1. The solution must adhere to ISO 27001.
  2. Change control of the hosting vCloud platform is not under full control of the internal business.
  3. The hosting provider outsources the platform support to the platform vendor.
  4. The applications to be deployed on the production hosts are not fully developed, although a beta exists.

Answer(s): B

Explanation:

The technical design process enables the platform designer to work in a methodical way and with others who have similar objectives. A risk is that a project item could potentially prevent the vision or aspects of it (requirements) from being created.
Chapter 1, The Technical Design Process



A DR project requires a recovery time objective (RTO) of 4 hours and has a recovery point objective (RPO) of 2 hours. The system fails at 8 p.m. on a Sunday evening. At what time is the application expected to be available to the end users?

  1. Midnight
  2. 10 p.m.
  3. 2 a.m.
  4. 11 p.m.

Answer(s): A

Explanation:

The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure. Chapter 3, RTO, RPO, and All That Stuff?