An earned value-based project control system can use either of which two budgets as the basis of its calculations?

  1. Labor hours or dollars.
  2. Direct or indirect cost.
  3. Earned or budgeted cost yearly.
  4. Linear feet or dollars.

Answer(s): A



Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  1. C.
  2. S.
  3. W.

Answer(s): C



Under which circumstance should one perform resource-leveling calculations?

  1. When the contract contains a provision for float-banking.
  2. When you believe that known resource limitations may override schedule logic.
  3. Never, unless required by the contract.
  4. When the schedule is resource-loaded.

Answer(s): B



Resource planning must take all of the following into account except for

  1. Types of materials, equipment and labor skills required to complete the project.
  2. Earned value techniques established for the project.
  3. Time available to complete the project.
  4. Cash flow (expenditure) limitations for completing work on the project.

Answer(s): B