Free CCP Exam Braindumps (page: 12)

Page 12 of 29


The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What is the cost index value of copper at the end of Year 2? (rounded to 2 decimal positions)

  1. 4.62
  2. 4.24
  3. 4.10
  4. 4.31

Answer(s): D




The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

  1. 8.7%
  2. 8.2%
  3. 4.6%
  4. 8.0%

Answer(s): D




The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
At the end of 30 months, copper prices will have increased by what percentage over today's price?

  1. 4.6%
  2. 3.5%
  3. 6.6%
  4. 2.5%

Answer(s): D




The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4?

  1. $1890/ton
  2. $1863/ton
  3. $1948/ton
  4. $1836/ton

Answer(s): D



Page 12 of 29



Post your Comments and Discuss AACE International CCP exam with other Community members:

Marry Clear commented on September 18, 2020
Very easy purcahse process. The material is well formatted and the Xengine Exam Simualtero is very cool and intuative. I am happy with my purcahse
CANADA
upvote