Free CCP Exam Braindumps (page: 15)

Page 15 of 29

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your
response/choice of responses.
What class of estimate is used for the preliminary design phase of a project?

  1. Class 5 - order of magnitude estimate with +50% / -30% accuracy
  2. Class 1 - order of magnitude with +30% / -30% accuracy
  3. Class 4 - budget estimate with +30% / -15% accuracy
  4. Class 2 - definitive estimate with +15%/-5% accuracy

Answer(s): A



A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
What information is needed to develop a Class 2 definitive estimate?

  1. Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates
  2. Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs
  3. Square footage of facilities, factored indirects and home office costs
  4. Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied

Answer(s): A



A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Select the statement that best describes the method to estimate the cost of the new rides:

  1. Break down the technology into components
  2. Call vendors for quotes
  3. Use historical data from past projects
  4. Adjust known data from existing rides

Answer(s): D



A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.
The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.
Why is a +/- notation necessary when developing an estimate?

  1. Contingency cushion
  2. It makes up for the lack of time to develop a real estimate
  3. It is a government requirement
  4. There are unknowns that affect the final cost of a project

Answer(s): D



Page 15 of 29



Post your Comments and Discuss AACE International CCP exam with other Community members:

Marry Clear commented on September 18, 2020
Very easy purcahse process. The material is well formatted and the Xengine Exam Simualtero is very cool and intuative. I am happy with my purcahse
CANADA
upvote