What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.

  1. Engineer
  2. Alternate
  3. Project Manager
  4. Agent

Answer(s): D



Budgeted cost of work scheduled is all of the following except:

  1. Total costs incurred in accomplishing work in a given-time period
  2. Baseline for performance measurement
  3. Sum of the budgets for work scheduled
  4. Includes portion of the budget for level-of-effort work

Answer(s): D



Which of the following is NOT an aspect of quality management?

  1. Quality assurance
  2. Quality planning
  3. Quality checking
  4. Quality control

Answer(s): C



Cost performance index (CPI) is defined by AACE International as: (assume no change in
budgeted quantities)

  1. ACWP/BCWS
  2. BCWS/BCWP
  3. ACWP/BCWP
  4. BCWP/ACWP

Answer(s): D



Page 1 of 29



Post your Comments and Discuss AACE International CCP exam with other Community members:

Daniel commented on February 03, 2025
Very Helpful
Anonymous
upvote

Daniel commented on February 03, 2025
Good way to prepare
Anonymous
upvote

Marry Clear commented on September 18, 2020
Very easy purcahse process. The material is well formatted and the Xengine Exam Simualtero is very cool and intuative. I am happy with my purcahse
CANADA
upvote