What do you call a person authorized to represent another (the principal) in some capacity? He/she can only act within this capacity or "scope of authority" to bind the principal.

  1. Engineer
  2. Alternate
  3. Project Manager
  4. Agent

Answer(s): D



Budgeted cost of work scheduled is all of the following except:

  1. Total costs incurred in accomplishing work in a given-time period
  2. Baseline for performance measurement
  3. Sum of the budgets for work scheduled
  4. Includes portion of the budget for level-of-effort work

Answer(s): D



Which of the following is NOT an aspect of quality management?

  1. Quality assurance
  2. Quality planning
  3. Quality checking
  4. Quality control

Answer(s): C



Cost performance index (CPI) is defined by AACE International as: (assume no change in
budgeted quantities)

  1. ACWP/BCWS
  2. BCWS/BCWP
  3. ACWP/BCWP
  4. BCWP/ACWP

Answer(s): D



Page 1 of 29



Post your Comments and Discuss AACE International CCP exam with other Community members:

Marry Clear commented on September 18, 2020
Very easy purcahse process. The material is well formatted and the Xengine Exam Simualtero is very cool and intuative. I am happy with my purcahse
CANADA
upvote