Aside from predecessors, resource manager assignments, and system administrator settings, what are three prerequisites for using the Resource Planner and Workload Balancer? (Choose three.)
- Job Roles assigned to Tasks
- Task Planned Hours greater than zero
- Task Durations greater than zero
- Schedules added to templates
- Time off logged in User Schedules
Answer(s): A,B,C
Explanation:
Objective: Identify prerequisites for using the Resource Planner and Workload Balancer.
Prerequisites:
Prerequisite 1: Job Roles assigned to Tasks
Assigning job roles helps in resource allocation and planning within the Resource Planner and Workload Balancer.
Prerequisite 2: Task Planned Hours greater than zero
Tasks need to have planned hours to be considered in the resource planning and workload balancing.
Prerequisite 3: Task Durations greater than zero
Tasks must have a duration set to be included in the workload calculations.
Reference:
These prerequisites are detailed in the Workfront documentation on resource management and task settings.