A manager needs to create a Request queue that tracks requests for Creative assets and Website changes, and assigns the requests to different teams for follow-up.
Which steps must be completed to meet this need?

  1. Create two Routing Rules Create two Topic Groups Assign Routing Rules to respective Topic Groups
  2. Create two Routing Rules m Create two Queue Topics
    Assign Routing Rules to respective Queue Topics
  3. Create two Topic Groups Create two Queue Topics Assign Queue Topics to respective Topic Groups

Answer(s): B

Explanation:

Objective: Track requests for creative assets and website changes and assign them to different teams.
Steps:
Step 1: Create two separate routing rules, one for creative assets and one for website changes. Step 2: Create two queue topics corresponding to the types of requests. Step 3: Assign each routing rule to the respective queue topic. This structure ensures that each type of request is properly categorized and routed to the appropriate team for follow-up.


Reference:

These steps are detailed in the Workfront documentation on setting up routing rules and queue topics.



An organization captures project requests in a request queue. Once the request has been triaged, it is converted into a project and the information captured in the request custom form should be carried over to the project.
How would a developer achieve this?

  1. Create a multi-object custom form with both the project and issue object types selected
  2. Create a project template and attach an issue custom form
  3. Check the box in the queue details to transfer the issue custom form to a project

Answer(s): C

Explanation:

In Adobe Workfront, when an organization captures project requests in a request queue and wants the information from the request custom form to be transferred to the project upon conversion, the developer should use the feature in the queue setup. Specifically, there is an option within the queue details where a checkbox can be selected to ensure that the custom form associated with the issue is transferred to the project. This allows all the information captured in the request custom form to be carried over seamlessly to the new project.



A portfolio manager has deleted a portfolio that is no longer relevant to the business strategy.
Which is a result of this action in Workfront?

  1. Programs and projects associated with the portfolio are deleted
  2. Programs associated with the portfolio are deleted.
  3. Projects associated with the portfolio are deleted.

Answer(s): B

Explanation:

In Adobe Workfront, if a portfolio manager deletes a portfolio, the immediate effect is that all programs associated with that portfolio are also deleted. However, the projects associated with those programs remain intact but will no longer be associated with any portfolio or program unless they are reassigned. This hierarchical deletion ensures that while the structural organization (programs) under the portfolio is removed, the actual project data remains unaffected and can be reassigned or restructured as needed.



A project manager is using information in the Portfolio Optimizer to analyze which projects to prioritize.
Where is this information coming from?

  1. The project's Alignment Score
  2. The project's Baseline
  3. The project's Business Case

Answer(s): A

Explanation:

The Portfolio Optimizer in Adobe Workfront is a tool used by project managers and portfolio managers to analyze and prioritize projects. The information used in the Portfolio Optimizer primarily comes from the project's Alignment Score. This score is a calculated metric that reflects how well a project aligns with the strategic goals and priorities of the organization. The Alignment Score helps in objectively comparing and prioritizing projects based on their strategic value.