The risk assessment programme which focuses on process unit design and operating practices and their adequacy given the unit's current or anticipated operating conditions

  1. Rbi
  2. Pha.
  3. Hazop
  4. Rcm

Answer(s): C



The program that is focused on understanding failure modes, addressing the modes and therefore improving the reliability of equipment and process facilities.

  1. Rbi
  2. Pha
  3. Rem
  4. Hazop

Answer(s): D



The programme that focused on maintaining the mechanical integrity of pressure equipment items and minimizing the risk of loss of containment due to deterioration

  1. Rbi
  2. Pha
  3. Rem
  4. Hazop

Answer(s): A



........Is not a substitute for a process hazards analysis (pha) or hazop

  1. Rbi
  2. Pha
  3. Rem
  4. Hazop

Answer(s): B



The following types of pressurized equipment and associated components covered by rbi

  1. Rotating equipment
  2. Turbines
  3. Pressurized pumps

Answer(s): A