Which of the following is/are included in five major levels in the manufacturing planning and control system?

  1. Strategic business plan
  2. Production plan
  3. Master production schedule
  4. All of these

Answer(s): D



Each level of MPC (Manufacturing planning and control) differs in the following:

Purpose of the plan
Planning Horizon
Level of detail
Planning Cycle

Since each level is:

  1. For different time span
  2. Responsible for satisfying market demand
  3. For different purposes
  4. Both A and C

Answer(s): D



1) What are the priorities-How much of what is to be produced and when?
2) What is available capacity-What resources do we have?
3) How can differences between priorities and capacity be resolved? These questions must be answered:

  1. During material resource planning
  2. During priority planning
  3. At each level of MCP
  4. During capacity planning

Answer(s): C



Strategic business plans are usually reviewed

  1. After each quarter
  2. Every six months to a year
  3. After five years
  4. Both A and B

Answer(s): B



Page 14 of 148



Post your Comments and Discuss APICS CPIM exam with other Community members:

Parsad commented on October 23, 2020
I asked for more discount as I needed to buy 3 exams. They gave me 35% discount The code is 35%OFF for anyone who wants to use.
INDIA
upvote