Which one of the following is NOT an input to master production schedule (MPS)?

  1. Forecasts for individual end items
  2. Sales orders
  3. Inventories and existing capacity
  4. Bill of materials

Answer(s): D



For master production schedule planning horizon usually extends from:

  1. 3-18 months
  2. 6-18 months
  3. 9-18 months
  4. None of these

Answer(s): A



In MPS, plans are reviewed and changed:

  1. Weekly
  2. Quarterly
  3. Weekly or Monthly
  4. Monthly

Answer(s): C



______________shows the quantities needed and when manufacturing intends to make use or use them.

  1. MPS
  2. Production plan
  3. Purchasing and production activity control
  4. Material Requirement Plan

Answer(s): D