Over the time span of the production plan, large changes in capacity are usually not possible. Additions or subtractions in plant and equipment are impossible or very difficult to accomplish in this period. However, some changes can be done. Which of the following are out of those variations?
Answer(s): D
Production planning problem typically has the following characteristics EXCEPT:
Answer(s): C
Basic strategies that can be used in a production plan may be:
A company wants to produce 10, 000 units of an item over the next three months at a level rate. The first month has 20 working days; the second, 21 working days; and the third, 12 working days because of an annual shutdown. On the average, how much should the company produce each day to level production?
Answer(s): B
The advantage/s of production leveling is/are: