A work center has 2 machines that are operated 16 hours a day for 5 days a week. Historically, the utilization has been 85% and the efficiency 105%. What is the rated capacity for this work center? (Rounded)

  1. 71
  2. 99
  3. 130
  4. 143

Answer(s): D



Which of the following is an input to capacity requirements planning (CRP)?

  1. Bills of material (BOM)
  2. Lot-sizing rules
  3. Open shop orders
  4. Standard cost

Answer(s): C



At which of the following levels does sales and operations planning take place?

  1. Component
  2. Finished goods
  3. Product family
  4. Market

Answer(s): C



Which of the following circumstances will cause a decrease in a work center's utilization?

  1. Working overtime
  2. Working below standard
  3. Lack of materials
  4. Rework operations

Answer(s): C