Which of the following capacity management techniques is used to support the production plan?

  1. Resource planning
  2. Capacity requirements planning
  3. Rough-cut capacity planning
  4. Input/output control

Answer(s): A



Which of the following statements describes the difference between capacity requirements planning and material requirements planning ?

  1. Material requirements planning ignores capacity constraints.
  2. Capacity requirements planning accounts for material.
  3. Material requirements planning is confined by capacity constraints.
  4. Capacity requirements planning only accounts for critical resources.

Answer(s): A



Which of the following four plant types for the theory of constraints processes one raw material into one final product?

  1. V-plant
  2. A-plant
  3. T-plant
  4. I-plant

Answer(s): D



If the quantity ordered equals the quantity required in a time bucket, which of the following lot -sizing rules has been used?

  1. Lot-for-lot
  2. Fixed order quantity
  3. Order "N" periods supply
  4. Economic order quantity (EOQ)

Answer(s): A



The ABC approach to inventory management is used primarily to:

  1. minimize transportation and material handling costs.
  2. classify inventory according to the total amounts of inventory required.
  3. optimize the amount of inventory for all classifications of inventory.
  4. establish the degree of inventory control required.

Answer(s): D