A kanban shop floor control system has which of the following characteristics?

  1. Large lot sizes
  2. Fixed routings
  3. Fixed worker assignments
  4. Forward scheduling

Answer(s): B



When an order is split into two orders, the immediate effect on a job shop work center is to increase which of the following elements?

  1. Setup time
  2. Work-in-process quantity
  3. Run time
  4. Lot size

Answer(s): A



The utilization of a downstream nonbottleneck resource is determined by:

  1. a bottleneck resource.
  2. theoretical capacity.
  3. available capacity.
  4. standard hours available.

Answer(s): A



Structured problem solving provides what essential result to an organization?

  1. Recognition of problems in the company's competitive position
  2. Resolution of problems of other organizations in like markets or with similar customers
  3. Recognition of problems with the company's management team
  4. Resolution of both strategic and operational problems

Answer(s): D