Mixed-model scheduling results in which of the following benefits:

  1. Improved efficiency
  2. Less headcount required
  3. Lower finished goods inventory
  4. Increased forecast accuracy

Answer(s): C



Manufactured parts are being assembled on a production line at a constant rate when a faulty component is identified. An assembly worker pushes the line stop button and work ceases while the defect is reviewed. This action is an example of:

  1. heijinka.
  2. andon.
  3. jidoka.
  4. kaizen.

Answer(s): C



A kanban shop floor control system has which of the following characteristics?

  1. Large lot sizes
  2. Fixed routings
  3. Fixed worker assignments
  4. Forward scheduling

Answer(s): B



When an order is split into two orders, the immediate effect on a job shop work center is to increase which of the following elements?

  1. Setup time
  2. Work-in-process quantity
  3. Run time
  4. Lot size

Answer(s): A



The utilization of a downstream nonbottleneck resource is determined by:

  1. a bottleneck resource.
  2. theoretical capacity.
  3. available capacity.
  4. standard hours available.

Answer(s): A