Free CPIM-ECO Exam Braindumps (page: 8)

Page 7 of 27

Based on the theory of constraints (TOC) scheduling approach, smaller lots created as a result of splitting order quantities are considered to be:

  1. period order quantities.
  2. bottleneck batches.
  3. transfer batches.
  4. campaign orders.

Answer(s): C



In an attempt to reduce costs associated with information system transactions, which of the following approaches should be considered?

  1. Discontinue backflushing components
  2. Reducing levels in the bill of material
  3. Remove the component supermarket
  4. Reducing lot sizes of manufactured products

Answer(s): B



Which of the following statements about the MRP due date for a shop order is true?

  1. It is the same as operation priority.
  2. It is used in deriving operation priority.
  3. It is established at order release time and frozen until order completion.
  4. It is equal to the due date plus 5 "M" days.

Answer(s): B



Which item is a role of the six sigma champion?

  1. Acting as an internal six sigma consultant
  2. Removing barriers the teams eccounter
  3. Providing technical support and mentoring
  4. Identifying possible causes of the problem

Answer(s): B






Post your Comments and Discuss APICS CPIM-ECO exam with other Community members: