The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

  1. Focus on the business need.
  2. Deliver on time.
  3. Collaborate.
  4. Never compromise quality.

Answer(s): C



View Related Case Study

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the agreement of the team.

Which Agile principle MOST influences this course of action?

  1. Deliver on time.
  2. Never compromise quality.
  3. Build incrementally from firm foundations.
  4. Develop iteratively.

Answer(s): A



View Related Case Study

HOTSPOT (Drag and Drop is not supported)

Answer the following question about how risks will be reduced on the Hoy Hall Hotel project through successful application of the DSDM Principles.

Column 1 lists a selection of project risks identified on the Hoy Hall Hotel project. Column 2 is a list of the DSDM Principles. For each risk in Column 1, select from Column 2 the DSDM Principle which, if applied appropriately, would MOST help to reduce or mitigate that risk.

Each selection from Column 2 can be used once, more than once or not at all.



  1. See Explanation section for answer.

Answer(s): A

Explanation:

Here are the DSDM Principles that would most help to reduce or mitigate the listed risks:
The `Hoy for Hoy Hall' Action Group may cause delay to the project if they are not kept updated on how the finished rooms are going to look.
G: Communicate continuously and clearly
Timber Tigers will ensure that the front rooms are finished and approved by the end of Timebox A.
E: Build incrementally from firm foundations
The Architecture Angels IT support team may require more detail up front in order to approve the initial design for the new online reservation system.
A: Focus on the business need
The morale of the Solution Development Team may be adversely affected if the external web design specialist is not a team player.
C: Collaborate

Empowering the Solution Development Team to manage themselves on a day-to-day basis may result in the Project Manager losing sight of what activities are being carried out, by whom and when.
H: Demonstrate control



View Related Case Study

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying controls to the end of Development Timebox C.

What action should the Project Manager take when considering the End of Timebox Review?

  1. Encourage the Marketing Director to attend the End of Timebox Review.
  2. Attend the next Daily Stand-up to raise an issue about the windows.
  3. Prepare a summary of progress against plan, for presentation at the review.
  4. Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.

Answer(s): C