Free AgilePM-Practitioner Exam Braindumps
Agile Project Management (AgilePM) Practitioner Questions 51–55 (page: 12)

Updated On: 10-Feb-2026
View Related Case Study

During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what needed to be done before these would be acceptable.

Is this an appropriate application of Agile Project Management for this project?

  1. Yes, because this will enable the Solution Development Team to ensure they are on track to deliver a viable solution.
  2. Yes, because this allows each team member working in the Timebox to provide a short progress report and raise any issues that hinder their progress.
  3. No, because early and frequent visibility of the product features will maintain engagement with the stakeholders.
  4. No, because only members of the Solution Development Team are permitted to attend Review Sessions.

Answer(s): A



View Related Case Study

The Business Sponsor threatened to stop funding if there was no evidence of tangible progress. To reduce this risk, the Business Sponsor was invited to several walk- rounds of the new bedroom and en-suite bathroom facilities throughout the project.

Is this an appropriate application of Agile Project Management for this project?

  1. Yes, because the early and frequent demonstration of product features to the Business Sponsor increases the visibility of the project and keeps the business engaged.
  2. Yes, because the project's budget holder is the only person who can approve project products.
  3. No, because products should be handed over at the end of the project, during Post-Project.
  4. No, because the Daily Stand-up meetings should have allowed the key representatives to review and discuss the evolving solution.

Answer(s): A



View Related Case Study

During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re- engage this group and explore discrepancies in understanding.

Is this an appropriate application of Agile Project Management for this project?

  1. Yes, because Facilitated Workshops provide a forum for each member of the team to present a short progress report.
  2. Yes, because discussing requirements in the presence of other stakeholders increases the whole group's awareness.
  3. No, because the Project Manager should have escalated this disagreement as an issue before any action was taken.
  4. No, because the local Action Group should have attended the Daily Stand-up meetings.

Answer(s): B



View Related Case Study

Answer the following questions about the contents of the DSDM products.

Each of the following questions includes true statements about the project but only two statements are appropriate entries for the DSDM product identified.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements represent appropriate entries for the Business Case?

  1. A list of high-level functional and non-functional requirements that the project should meet written as User Stories.
  2. Coffee shops that sell Fairtrade products and alcohol from local breweries out perform other coffee shops in the market.
  3. The Sales Manager has been asked to produce a report within the next two days showing the number of generic insurance policies sold to coffee shops over the past three years.
  4. The Sales Manager has calculated that the new coffee shop insurance product will increase revenues by 10% each week.
  5. Market research shows that the number of coffee shop patrons taking legal action against retailers has increased by 200% over the past two years.

Answer(s): D,E

Explanation:

For the XAN Insurance Company Web Project and considering the Agile Project Management approach, particularly the Dynamic Systems Development Method (DSDM) framework which emphasizes business value and active user involvement, the Business Case should justify the project in terms of cost, benefit, and risk.
Selected Statements for the Business Case:
D: The Sales Manager has calculated that the new coffee shop insurance product will increase revenues by 10% each week.
E. Market research shows that the number of coffee shop patrons taking legal action against retailers has increased by 200% over the past two years.
D: This statement provides a clear financial projection for the benefits of the project, which is a critical component of a Business Case. It quantifies the expected revenue increase, offering a tangible benefit to justify the project investment.
E: This statement outlines a market trend that necessitates the project, highlighting the increased demand for insurance due to rising legal actions against coffee shops. It underscores the relevance and timeliness of the project, adding to the justification for undertaking the project.
Why Other Statements Are Excluded:
A: While high-level functional and non-functional requirements are essential for project planning, they typically belong in project requirements documentation or the Project Brief, rather than the

Business Case.
B: This statement provides market insight but does not directly justify the project from a cost- benefit-risk perspective. The relevance of selling Fairtrade products and alcohol to the insurance product project is tangential.
C: The request for a report on past sales provides background information but does not in itself justify the project investment. It might be used to inform the Business Case but is not a direct component of it.



View Related Case Study

Which 2 statements represent appropriate entries for the Prioritised Requirements List?

  1. Creation of a new coffee shop insurance product on the existing website is expected to increase the insurance company's revenues by up to 10% per week.
  2. All correspondence sent to coffee shop owners by the new system should contain the XAN logo in the top left hand corner of the page.
  3. Further website developments to allow existing customers to access services online are NOT to be included within the scope of this project.
  4. The Business Visionary will provide a formal acceptance of the coffee shop insurance product.
  5. An assessment will be made of the effectiveness of the techniques used on the project, in line with the principles of Agile Project Management.

Answer(s): B,C



Viewing page 12 of 28
Viewing questions 56 - 60 out of 184 questions