The first and most important step, in establishing a good corporate quality plan is

  1. Determining customer requirements.
  2. Determining manufacturing process capabilities.
  3. Evaluation vendor quality systems.
  4. Ensuring quality participation in design review.

Answer(s): A



When planning quality control functions, which one of the following is MOST directly related to production of a quality product?

  1. Process control and process capability.
  2. Suitable blueprints.
  3. Dimensional tolerancing.
  4. Product audits.

Answer(s): A



Which of the following would be the MOST important considerations when establishing inspection points within a production operation?

I). Inspection to prevent defects from entering the system.
II). Inspection after all operations (both manual and automated).
III). Inspection prior to a painting or masking operation.

  1. I only
  2. I and II only
  3. I and III only
  4. I, II and III

Answer(s): C



The primary reason that nonconforming material should be identified and segregated is

  1. So that the cause of nonconformity can be determined.
  2. So it cannot be used in production without proper authorization.
  3. To obtain samples of poor workmanship for use in the company's training program.
  4. So that responsibility can be determined and disciplinary action taken.

Answer(s): B



Of the services listed below, which one performed by design engineering is of particular interest to QA personnel?

  1. Audit reports.
  2. Cost reports.
  3. Change action.
  4. Rework criteria.

Answer(s): C