Free ATLASSIAN ACP-620 Exam Questions (page: 6)

You shared a URL to the dashboard with Bobby but when he looks at it, the gadgets return errors that state, "The filter configured for this gadget could not be retrieved."

What is the most likely problem with the filters?

  1. They return issues from team-managed projects.
  2. They return issues with hidden fields.
  3. They are not shared with Bobby.
  4. They contain corrupt JQL clauses.

Answer(s): C

Explanation:

The error "The filter configured for this gadget could not be retrieved" typically means that the filters used in the dashboard gadgets are not shared with Bobby. Even if Bobby has access to the projects or issues, he cannot see the results unless the filters themselves are explicitly shared with him.



Teams using Project A and B currently use their own respective Scrum boards.

They must now work together on the same products and issues and in the same sprints.

You created a new Scrum board based on this filter:

project in (A,B) ORDER BY Rank ASC

You must also check two settings to make sure the teams can access and use the new board.

Identify the two settings. (Choose two.)

  1. application access of all team members
  2. global permissions of all team members
  3. availability of parallel sprints
  4. sharing on the board sub-filter
  5. sharing on the board filter
  6. project permissions

Answer(s): E,F

Explanation:

Sharing on the board filter: The board filter must be shared with all users who need access to the board; otherwise, they won't be able to view or use it.

Project permissions: Users must have the necessary permissions (such as Browse Projects and Manage Sprints) on both Project A and Project B to view issues and manage sprints on the new shared board.



Your team needs a new board that:

only shows issues that are actively in progress allows a separate area to prioritize incoming work allows them to release issues from the Done column

Identify the correct solution to meet these requirements

  1. Create a scrum board and enable the backlog!
  2. Create a scrum board and configure swimlanes.
  3. Create a kanban board and enable column constraints.
  4. Create a scrum board and configure a quick filter.
  5. Create a kanban board and enable the backlog.
  6. Create a kanban board and configure swimlanes

Answer(s): E

Explanation:

A Kanban board with the backlog enabled meets all the requirements: it shows only in-progress issues (via column configuration), provides a separate area to prioritize incoming work (the Kanban backlog), and allows for releasing issues from the Done column (via version management or Kanban releases).



A team needs a board that meets these requirements:

All issues can be moved across the entire workflow on a single view of the board.

Issues can be worked in a continuous flow without start and stop dates.

Which board configuration meets the requirements?

  1. Kanban board without backlog
  2. Scrum board without parallel sprints
  3. Scrum board with swimlanes
  4. Kanban board with backlog

Answer(s): A

Explanation:

A Kanban board without backlog displays all issues on a single view and supports a continuous workflow without start and stop dates. This setup is ideal for teams using a continuous delivery process, allowing issues to move freely across the entire workflow.