[Managing AV Projects]



According to the Gantt chart pictured, the Project Manager should wait to start Activity C until which predecessor has been reached?

  1. Week 3
  2. Week 4
  3. Activity B
  4. Milestone X

Answer(s): D



[Performing Maintenance and Servicing]

As part of a service agreement offering, wfwt PRIMARY role do preventive maintenance visits (PM/PMV) play?

  1. allows the AV provider toclean, service and assess equipment In the field on a regular basis
  2. allows the AV provider to check in with customer and serves as an opportunity to sell further solutions
  3. allows the AV provider tosell a service that is often forgotten by the customer, and therefore generate greater profit
  4. allows the AV provider access to client premises and scope future work

Answer(s): A



[Developing AV Solutions]
Which frequencies are amplified by a subwoofer?

  1. lowest
  2. mid-low
  3. mid-high
  4. highest

Answer(s): A



HOTSPOT
[Developing AV Solutions]
Which section of the Ohm's Law chart should be used to calculate values expressed in Ohms? Select the answer by clicking anywhere within the correct quadrant.

  1. See Explanation for the Answer.

Answer(s): A

Explanation:



[Conducting a Needs Assessment]
When doing a site survey, it is MOST IMPORTANT to consider the client's

  1. budget.
  2. timeline.
  3. expectations.
  4. knowledge of technology.

Answer(s): C