The business case for project XCON has been signed off and money has been allocated. The business analyst on the project wants to understand who the stakeholders are. how much authority they have, and how much involvement they want in the project so that a stakeholder management plan can be created.
Which technique SHOULD the business analyst use to gain this understanding?

  1. CATWOE
  2. Power / Interest Grid.
  3. RACI chart
  4. Resource audit

Answer(s): B

Explanation:

A Power / Interest Grid is a technique for analysing and managing stakeholders based on their level of power and interest in an organisation or project. It helps to identify who are the key stakeholders and how they should be engaged and communicated with. Therefore, option B is the correct answer, as a Power / Interest Grid would help the business analyst to gain an understanding of who the stakeholders are, how much authority they have, and how much involvement they want in the project so that a stakeholder management plan can be created. A Power / Interest Grid would help to classify stakeholders into four categories based on their level of power and interest: high power, high interest; high power, low interest; low power, high interest; low power, low interest. A Power /

Interest Grid would help to determine different stakeholder management strategies for each category: active and constant management; keep satisfied; keep informed; watch. Option A is not a correct answer, as CATWOE is not a technique for analysing and managing stakeholders based on their level of power and interest. CATWOE is a technique for exploring stakeholder business perspectives by identifying six elements: Customer, Actor, Transformation, Worldview, Owner and Environment. It helps to understand how different stakeholders perceive a business situation or problem and what they expect from a solution. Option C is not a correct answer, as RACI chart is not a technique for analysing and managing stakeholders based on their level of power and interest. RACI chart is a technique for defining roles and responsibilities of stakeholders in relation to tasks or activities within an organisation or project. It helps to identify who are Responsible, Accountable, Consulted or Informed for each task or activity. Option D is not a correct answer, as resource audit is not a technique for analysing and managing stakeholders based on their level of power and interest.

Resource audit is a technique for identifying and evaluating the resources that an organisation has or needs to achieve its objectives. It helps to assess the availability and quality of an organisation's resources, such as human, physical, financial and intangible resources.


Reference:

BCS Practitioner Certificate in BAP Specimen, page 39.



A business analyst is reviewing the stakeholder management strategy for a project seeking to implement a new IT system to monitor the effectiveness of social work interventions. Three stakeholders have been identified.
1. Head of Monitoring and Evaluation is the project sponsor
2. The monitoring and evaluation officer working in the Head of Monitoring and Evaluation's team who is eager to get the project implemented as it will transform his role 3 The financial accountant assigned to the project to monitor the financial benefits of the new system This role is essential to the project, but he isn't interested in the detail. The analyst has identified stakeholder management strategies for two of the three stakeholders 'active and constant management' and 'keep onside'
Based on the information presented in the scenario, which further strategy is required?

  1. Keep satisfied
  2. Watch
  3. Ignore
  4. Keep informed

Answer(s): A

Explanation:

A stakeholder management strategy is a plan for engaging and communicating with stakeholders based on their level of power and interest in an organisation or project. It helps to ensure that stakeholders are appropriately involved and informed throughout the organisation's or project's lifecycle. Therefore, option A is the correct answer, as keep satisfied is the further strategy that is required for one of the three stakeholders in this scenario. Keep satisfied is the strategy for managing stakeholders who have high power but low interest in an organisation or project. It involves meeting their needs and expectations without over-communicating or over-involving them. The stakeholder who requires this strategy in this scenario is the financial accountant assigned to the project to monitor the financial benefits of the new system. This stakeholder has high power, as he is essential to the project and can influence its outcome. However, he has low interest, as he is not interested in the detail of the project. Option B is not a correct answer, as watch is not the further strategy that is required for any of the three stakeholders in this scenario. Watch is the strategy for managing stakeholders who have low power and low interest in an organisation or project. It involves monitoring their behaviour and attitude without engaging or communicating with them too much. None of the stakeholders in this scenario have low power and low interest, as they are all involved or affected by the project in some way. Option C is not a correct answer, as ignore is not a valid strategy for managing any stakeholder in an organisation or project. Ignore is the strategy of disregarding or neglecting stakeholders who have no power or interest in an organisation or project. It involves excluding them from any engagement or communication activities. This strategy is not advisable, as it may lead to stakeholder dissatisfaction, resentment or resistance. Option D is not a correct answer, as keep informed is not the further strategy that is required for any of the three stakeholders in this scenario. Keep informed is the strategy for managing stakeholders who have low power but high interest in an organisation or project. It involves providing them with regular and sufficient information and updates without overloading them with details. None of the stakeholders in this scenario have low power but high interest, as they are all involved or affected by the project in some way.


Reference:

BCS Practitioner Certificate in BAP Specimen, page 40.



You have been discussing Paurs recent project with him He explained that he had needed to spend considerable time interviewing stakeholders and was now behind plan You asked him why he didn't use a workshop to avoid delays.
Which of the following MIGHT Paul reply'? Select the THREE that apply

  1. One stakeholder has a dominant personality
  2. The stakeholders were located in different time zones
  3. Consensus from stakeholders needed to be established
  4. The challenge of organising key stakeholder diaries
  5. A neutral venue was available for stakeholder discussions

Answer(s): B,D,E

Explanation:

A workshop is a technique for conducting group discussions and activities with stakeholders to elicit, analyse, validate and prioritise their views and needs. It helps to facilitate effective communication and collaboration among stakeholders and resolve conflicts or issues. Therefore, options B, D and E are correct answers, as they are possible reasons why Paul did not use a workshop to avoid delays. They describe different challenges or constraints that may prevent or limit the use of a workshop technique. Option B describes a challenge related to the geographical location of stakeholders. If the stakeholders are located in different time zones, it may be difficult or impractical to arrange a workshop that suits their availability and preferences. Option D describes a challenge related to the availability of stakeholders. If the key stakeholders have busy or conflicting schedules, it may be hard or impossible to organise a workshop that involves all of them at the same time. Option E describes a constraint related to the venue of the workshop. If a neutral venue is available for stakeholder discussions, it may be preferable or necessary to use it instead of a workshop, as it may reduce bias or influence from any stakeholder group. Option A is not a correct answer, as it is not a reason why

Paul did not use a workshop to avoid delays. It describes an issue that may arise during a workshop, but not prevent or limit its use. If one stakeholder has a dominant personality, it may affect the dynamics and outcomes of the workshop, but it can be managed by using appropriate facilitation skills and techniques. Option C is not a correct answer, as it is not a reason why Paul did not use a workshop to avoid delays. It describes an objective that may be achieved by using a workshop, but not prevent or limit its use. If consensus from stakeholders needs to be established, it may be beneficial or essential to use a workshop, as it can help to reach a common understanding and agreement among stakeholders.


Reference:

BCS Practitioner Certificate in BAP Specimen, page 41.



A business analyst has been carrying out investigations into a problem situation However, it is clear to the business analyst that, even after a number of interviews with individual stakeholders, some stakeholder s views still conflict.
Which investigation technique SHOULD be used to resolve the conflict and gain a consensus?

  1. Scenario analysis.
  2. Questionnaire
  3. Observation
  4. Workshop

Answer(s): D

Explanation:

A workshop is a technique for conducting group discussions and activities with stakeholders to elicit, analyse, validate and prioritise their views and needs. It helps to facilitate effective communication and collaboration among stakeholders and resolve conflicts or issues. Therefore, option D is the correct answer, as a workshop would help the business analyst to resolve the conflict and gain a consensus among stakeholders who have different views after individual interviews. A workshop would help to bring together the conflicting stakeholders in one place and time and enable them to share and compare their views openly and constructively. A workshop would help to identify and address the sources and reasons of the conflict and find common ground and mutual understanding among stakeholders. A workshop would help to generate and evaluate different options or solutions that satisfy all or most of the stakeholder views and agree on the best one for further development and implementation. Option A is not a correct answer, as scenario analysis is not a technique for resolving conflict and gaining consensus among stakeholders who have different views after individual interviews. Scenario analysis is a technique for exploring how different scenarios or situations could affect the outcomes or impacts of an organisation or project. It helps to test the feasibility and desirability of different options or solutions under various circumstances or assumptions. Option B is not a correct answer, as questionnaire is not a technique for resolving conflict and gaining consensus among stakeholders who have different views after individual interviews. Questionnaire is a technique for collecting information from stakeholders by asking them predefined questions in written form. It helps to elicit quantitative or qualitative data from a large number of stakeholders in an efficient and consistent way. Option C is not a correct answer, as observation is not a technique for resolving conflict and gaining consensus among stakeholders who have different views after individual interviews. Observation is a technique for gathering information from stakeholders by watching them perform their tasks or activities in their natural environment. It helps to analyse how stakeholders work in practice and identify their implicit or tacit needs.


Reference:

BCS Practitioner Certificate in BAP Specimen, page 42.



Page 8 of 18



Post your Comments and Discuss BCS BAPv5 exam with other Community members:

Nikki Cruz commented on November 04, 2024
This was a life saver for me. I knew the material but these questions really helped me . Passed on my first attempt !
Anonymous
upvote

Emmanuel commented on November 04, 2024
Can a person pass AZ900 just by using this site only ?
SOUTH AFRICA
upvote

Tech Savvy commented on November 04, 2024
Great work team!, would be good if you list 10 questions at each page,
Anonymous
upvote

Jay commented on November 04, 2024
I tried to clear this exam for 3 times but failed. So I finally resorted to using these exam dumps which I really did not want to. But I was left with no choice.
New Zealand
upvote

Fernando commented on November 04, 2024
Very cool and very helpful. Bought 2 exams with 50% discount.
Brazil
upvote

Jai commented on November 03, 2024
I liked the questions
Anonymous
upvote

Sumitra commented on November 03, 2024
I am eager to write CAD exam
Anonymous
upvote

Veitnam commented on November 03, 2024
Thank you the website owner for making these exam questions available for free. It helped me clear my paper.
Anonymous
upvote

Anonymous commented on November 03, 2024
Can I pass the exams only with these dumps ?
Anonymous
upvote

Bin Mahamood commented on November 03, 2024
terraform { required_providers { aws = { version = ">= 2.7.0" source = "hashicorp/aws" } } }
Anonymous
upvote

Yizzy commented on November 02, 2024
@Patak when did you take the exam?
Anonymous
upvote

Tadele commented on November 02, 2024
Help full to next exam
Anonymous
upvote

Jaqulin commented on November 02, 2024
I appreciate the service and the questions being free. Finally something free in this world.
FRANCE
upvote

numan commented on November 02, 2024
really helping
GERMANY
upvote

Patak commented on November 01, 2024
I got about 70 to 74 questions are from here. So its worth it.
INDIA
upvote

xxx commented on November 01, 2024
I've used this material for exam preps. Many questions comes from this dump.
ESTONIA
upvote

Timens commented on November 01, 2024
Well done and nicely put together. All valid questions in PDF version.
Netherlands
upvote

Debendra commented on November 01, 2024
Passed the exam. The best Diwalli present!!! Thank you team for this braindumps.
INDIA
upvote

Tdk commented on November 01, 2024
Great staff
SOUTH AFRICA
upvote

Tdk commented on November 01, 2024
Good material
SOUTH AFRICA
upvote

Sophy commented on November 01, 2024
These communities along with the questions posted here assisted me a lot for passing my exam CISSP
UNITED STATES
upvote

Pear commented on November 01, 2024
I had a deadline to pass this exam. These questions dumps came to save me. Very easy and quite accurate.
UNITED STATES
upvote

Kiran P commented on November 01, 2024
very helpful ..
INDIA
upvote

Sree commented on October 31, 2024
This is a good practice test for preparation
UNITED STATES
upvote

ambr commented on October 31, 2024
just doing some preparation
Anonymous
upvote

Caml commented on October 31, 2024
Ok at thé moment
Anonymous
upvote

Caml commented on October 31, 2024
I will Say After trying more questions
Anonymous
upvote

George commented on October 31, 2024
Fun way to learn
ROMANIA
upvote

Damian commented on October 31, 2024
Just passed my exam today. I am going to focus on my second exam. Just an FYI, if you are buying the full version they have a buy 1 get one free deal. Just select 2 exams and add them to shopping cart and you get a 50% off your over all total... automatically.
UNITED STATES
upvote

Temitope commented on October 31, 2024
Good questions
EUROPEAN UNION
upvote

Temitope commented on October 31, 2024
Nice and well structured questions
EUROPEAN UNION
upvote

Mr. K commented on October 31, 2024
Valid exam dump. Passed in first try. Keep the good work and keep it free guys.
UNITED STATES
upvote

Fernanda commented on October 30, 2024
This is a very good practice test, I approve my exam
Anonymous
upvote

Gustavo Gonçalves commented on October 30, 2024
A questão 17 está errada a resposta é letra D. Podem corrigir por favor?
BRAZIL
upvote