A Test Manager conducts risk assessment for a project. One of the identified risks is: The sub- contractor may fail to meet his commitment". If this risk materializes. it will lead to delay in completion of testing required for the current cycle.
Which of the following sentences correctly describes the risk?

  1. It is a product risk since any risk associated with development timeline is a product risk.
  2. It is no longer a risk for the Test Manager since an independent party (the sub-contractor) is now managing it
  3. It is a object risk since successful completion of the object depends on successful and timely completion of the tests
  4. It is a product risk since default on part of the sub-contractor may lead to delay in release of the product

Answer(s): D

Explanation:

A product risk is a risk that affects the quality or timeliness of the software product being developed or tested1. Product risks are related to the requirements, design, implementation, verification, and maintenance of the software product2.
The risk of the sub-contractor failing to meet his commitment is a product risk, as it could cause a delay in the completion of the testing required for the current cycle, which in turn could affect the release date of the product. The release date is an important aspect of the product quality, as it reflects the customer satisfaction and the market competitiveness of the product3.
The other options are not correct because:
A . It is not true that any risk associated with development timeline is a product risk. Some risks could be project risks, which are risks that affect the management or control of the software project, such as budget, resources, schedule, or communication1. For example, a risk of losing a key project stakeholder is a project risk, not a product risk.
B . It is not true that the risk is no longer a risk for the Test Manager since an independent party is managing it. The Test Manager is still responsible for ensuring that the testing activities are completed according to the test plan and the quality objectives4. The Test Manager should monitor and control the sub-contractor's performance and communicate with him regularly to identify and mitigate any potential issues or deviations5.
C . It is not clear what is meant by "object" in this option, but it could be interpreted as the software system under test or the test object6. In any case, the risk is not an object risk, as it does not affect the successful completion of the object, but rather the successful completion of the testing of the object. An object risk could be a risk that affects the functionality, reliability, usability, efficiency, maintainability, or portability of the software system under test2. For example, a risk of the software system having a high complexity or a low testability is an object risk, not a product risk.
Reference =
1 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 97

2 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 98 3 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 99 4 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 100 5 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 101 6 ISTQB® Certified Tester Foundation Level Syllabus v4.0, 2023, p. 102



Who of the following has the best knowledge to decide what tests in a test project should be automated?

  1. The developer
  2. The customer
  3. The development manager
  4. The test leader

Answer(s): D

Explanation:

The test leader is the person who is responsible for planning, monitoring, and controlling the test activities and resources in a test project. The test leader should have the best knowledge of the test objectives, scope, risks, resources, schedule, and quality criteria. The test leader should also be aware of the test automation criteria, such as the execution frequency, the test support, the team education, the roles and responsibilities, and the devs and testers collaboration1. Based on these factors, the test leader can decide which tests are suitable for automation and which are not, and prioritize them accordingly. The test leader can also coordinate with the test automation engineers, the developers, and the stakeholders to ensure the alignment of the test automation strategy with the test project goals and expectations. Reference = ISTQB Certified Tester Foundation Level (CTFL) v4.0 Syllabus, Chapter 2, Section 2.3.1, Page 152; ISTQB Glossary of Testing Terms v4.0, Page 403; ISTQB Certified Tester Foundation Level (CTFL) v4.0 Syllabus, Chapter 6, Section 6.1.1, Page 514; Top 8 Test Automation Criteria You Need To Fulfill - QAMIND1



Which of the following are the phases of the ISTQB fundamental test process?

  1. Test planning and control, Test analysis and design, Test implementation and execution, Evaluating ex t criteria and reporting. Test closure activities
  2. Test planning, Test analysis and design. Test implementation and control. Checking test coverage and reporting, Test closure activities
  3. Test planning and control, Test specification and design. Test implementation and execution, Evaluating test coverage and reporting, Retesting and regression testing, Test closure activities
  4. Test planning. Test specification and design. Test implementation and execution. Evaluating exit criteria and reporting. Retesting and test closure activities

Answer(s): A

Explanation:

The ISTQB fundamental test process consists of five main phases, as described in the ISTQB Foundation Level Syllabus, Version 4.0, 2018, Section 2.2, page 15:
Test planning and control: This phase involves defining the test objectives, scope, strategy, resources, schedule, risks, and metrics, as well as monitoring and controlling the test activities and results throughout the test process.
Test analysis and design: This phase involves analyzing the test basis (such as requirements, specifications, or user stories) to identify test conditions (such as features, functions, or scenarios) that need to be tested, and designing test cases and test procedures (such as inputs, expected outcomes, and execution steps) to cover the test conditions. This phase also involves evaluating the testability of the test basis and the test items (such as software or system components), and selecting and implementing test techniques (such as equivalence partitioning, boundary value analysis, or state transition testing) to achieve the test objectives and optimize the test coverage and efficiency. Test implementation and execution: This phase involves preparing the test environment (such as hardware, software, data, or tools) and testware (such as test cases, test procedures, test data, or test scripts) for test execution, and executing the test procedures or scripts according to the test plan and schedule. This phase also involves logging the outcome of test execution, comparing the actual results with the expected results, and reporting any discrepancies as incidents (such as defects, errors, or failures).
Evaluating exit criteria and reporting: This phase involves checking if the planned test activities have been completed and the exit criteria (such as quality, coverage, or risk levels) have been met, and reporting the test results and outcomes to the stakeholders. This phase also involves making recommendations for the release or acceptance decision based on the test results and outcomes, and identifying any residual risks (such as known defects or untested areas) that need to be addressed or mitigated.
Test closure activities: This phase involves finalizing and archiving the testware and test environment for future reuse, and evaluating the test process and the test project against the test objectives and the test plan. This phase also involves identifying any lessons learned and best practices, and communicating the findings and suggestions for improvement to the relevant parties. Reference = ISTQB Certified Tester Foundation Level Syllabus, Version 4.0, 2018, Section 2.2, page 15; ISTQB Glossary of Testing Terms, Version 4.0, 2018, pages 37-38; ISTQB CTFL 4.0 - Sample Exam - Answers, Version 1.1, 2023, Question 88, page 32.



Which of the following issues cannot be identified by static analysis tools?

  1. Very low MTBF (Mean Time Between failure)
  2. Potentially endless loops
  3. Referencing a variable with an undefined value
  4. Security vulnerabilities

Answer(s): A

Explanation:

Static analysis tools are software tools that examine the source code of a program without executing it. They can detect various types of issues, such as syntax errors, coding standards violations, security vulnerabilities, and potential bugs12. However, static analysis tools cannot identify issues that depend on the runtime behavior or performance of the program, such as very low MTBF (Mean Time Between failure)3. MTBF is a measure of the reliability of a system or component. It is calculated by dividing the total operating time by the number of failures. MTBF reflects how often a system or component fails during its expected lifetime. Static analysis tools cannot measure MTBF because they do not run the program or observe its failures. MTBF can only be estimated by dynamic testing, which involves executing the program under various conditions and collecting data on its failures4. Therefore, very low MTBF is an issue that cannot be identified by static analysis tools. The other options, such as potentially endless loops, referencing a variable with an undefined value, and security vulnerabilities, are issues that can be identified by static analysis tools. Static analysis tools can detect potentially endless loops by analyzing the control flow and data flow of the program and checking for conditions that may never become false5. Static analysis tools can detect referencing a variable with an undefined value by checking the scope and initialization of variables and reporting any use of uninitialized variables6. Static analysis tools can detect security vulnerabilities by checking for common patterns of insecure code, such as buffer overflows, SQL injections, cross-site scripting, and weak encryption. Reference = What Is Static Analysis? Static Code Analysis Tools - Perforce Software, How Static Code Analysis Works | Perforce, Static Code Analysis: Techniques, Top 5 Benefits & 3 Challenges, What is MTBF? Mean Time Between Failures Explained | Perforce, Static analysis tools - Software Testing MCQs - CareerRide, ISTQB_Chapter3 | Quizizz, [Static Code Analysis for Security Vulnerabilities | Perforce].



Page 13 of 38



Post your Comments and Discuss BCS CTFL4 exam with other Community members:

Bannor commented on October 11, 2024
This exam is valid and legit. I purchased the full version last week and managed to pass. There are 2 or 3 wrong answers which I reported to the admin and they fixed it right away.
CANADA
upvote

Marko commented on October 11, 2024
Been using this website for a while now. I am a big fun as it has helped me pass 3 exams so far. I hope they can keep the site live.
EUROPEAN UNION
upvote

Ngoni commented on October 11, 2024
Great resource
ZIMBABWE
upvote

jeffrey commented on October 11, 2024
this is great
Anonymous
upvote

Soniksha commented on October 10, 2024
I purchased the full version of this exam and it turned out quire accurate. I passed with the help of this exam.
UNITED STATES
upvote

Sadiq commented on October 10, 2024
Test questions
Anonymous
upvote

Viktor commented on October 10, 2024
Respect to the owners and operators of this site for providing this free exam site.
CANADA
upvote

Deep commented on October 10, 2024
Good questions
INDIA
upvote

Goben commented on October 10, 2024
Passed in one shot.
GERMANY
upvote

Neo commented on October 10, 2024
Gets easier as you go along
SOUTH AFRICA
upvote

Neo commented on October 10, 2024
Need more practice
SOUTH AFRICA
upvote

Violet commented on October 10, 2024
Need more practice
SOUTH AFRICA
upvote

Neo commented on October 10, 2024
Challenging
SOUTH AFRICA
upvote

Kopano commented on October 10, 2024
Prep going well
SOUTH AFRICA
upvote

Harika Mudumby commented on October 10, 2024
great content
Anonymous
upvote

Neo commented on October 10, 2024
Happy with the material
SOUTH AFRICA
upvote

Emily commented on October 09, 2024
A bit challe
SOUTH AFRICA
upvote

a commented on October 09, 2024
SIMPLE QUESTIONS
Anonymous
upvote

Emily commented on October 09, 2024
grt resource
SOUTH AFRICA
upvote

robin commented on October 09, 2024
Im' done with clear in my mind
Anonymous
upvote

EDC commented on October 09, 2024
Passed this exam with a freaking 95% today.
Anonymous
upvote

Divyesh Arya commented on October 09, 2024
Nice questions
UNITED STATES
upvote

Harry commented on October 09, 2024
This platform is the best out of the exam dumps sites. I love it.
UNITED STATES
upvote

Ursela commented on October 09, 2024
Invested in the full version of this exam dump PDF version and it paid off. Passed with 89%.
UNITED STATES
upvote

Rakesh commented on October 08, 2024
The best dump with best price, join this site for proof. 100% guarantee of passing with 90% score
UNITED STATES
upvote

Rakesh commented on October 08, 2024
good The best dump with best price, join this site for proof. 100% guarantee of passing with 90% score
UNITED STATES
upvote

Rakesh commented on October 08, 2024
Good The best dump with best price, join this site for proof. 100% guarantee of passing with 90% score
UNITED STATES
upvote

Rakesh commented on October 08, 2024
Good dumps to practice.
UNITED STATES
upvote

ric commented on October 08, 2024
is it still vaild?
KOREA REPUBLIC OF
upvote

Bboy commented on October 08, 2024
So far so good
FRANCE
upvote

Bboy commented on October 08, 2024
nice questions
FRANCE
upvote

Gaurav commented on October 08, 2024
Good data thank you
Anonymous
upvote

Mike commented on October 08, 2024
Not bad at all
CANADA
upvote

max commented on October 08, 2024
great exam dumps
ROMANIA
upvote