What is the PERT estimate (in hours) for project design where:
- Optimistic time is 40 hours
- Most likely time is 50 hours
- Pessimistic time is 60 hours

  1. 40 hours
  2. 45 hours
  3. 50 hours
  4. 55 hours
  5. 60 hours

Answer(s): C



Select the appropriate task to complete the section 2.2 of the work breakdown structure below:
2. Technician
2.1 Install rack

2.2 _________
2.3 Place fiber
2.4 Terminate fiber
2.5 Test fiber

  1. Prepare as-built drawings
  2. Install connector housing
  3. Clean/polish connectors
  4. Specify fiber

Answer(s): B



All of the following are considered market or regional conditions that can impact construction costs EXCEPT:

  1. Displacement and relocation
  2. Construction time frame
  3. Other large projects in the area
  4. Seasonal effects on construction costs

Answer(s): A



Select the appropriate task to complete section 2.2 of the work breakdown structure (WBS) below:
2 Technician
2.1 Install cabling
2.2 __________
2.3 Activate wireless

  1. Install access point
  2. Clean work area
  3. Install pathway for cabling
  4. Confirm wireless coverage

Answer(s): A



What type of estimate is based on the cost of performing similar work in the past, adjusted for current job conditions?

  1. Analogous
  2. Parametric
  3. Engineering
  4. Ledger
  5. PERT

Answer(s): A