During demolition, the contractor discovers dry rot in some existing walls that are to remain. After reaching an agreement with the client and contractor on a solution, what should be issued before construction continues?

  1. a bulletin
  2. an addendum
  3. a change order
  4. a change directive

Answer(s): C



What is the MOST efficient lighting control system a designer can incorporate in a fifth floor, south- facing office suite?

  1. roller shades
  2. automatic timers
  3. daylighting sensors
  4. occupancy sensors

Answer(s): C



In which type of space would occupant load be calculated using net square footage?

  1. exercise room
  2. airport terminal
  3. museum exhibit

Answer(s): A



A contractor defaults on payments to a mechanical subcontractor. The subcontractor is protected and guaranteed payment by a

  1. payment bond
  2. mechanic's lien
  3. performance bond
  4. builder's risk insurance

Answer(s): A



A post-occupancy evaluation indicates that occupants are cold during winter months due to the building's HVAC system not performing according to design.
What would have prevented this situation?

  1. commissioning
  2. additional diffusers
  3. a punch (deficiency) list
  4. an underfloor distribution system

Answer(s): A