Which of the following are features of performance specification?1. Method of achieving the buyer's desired result2. What needs to be achieved when using the product3. Purposes of the product4. Technical and physical characteristics of the product
Answer(s): D
There are 2 major types of specifications:1. Performance specificationsThese are Specifications that define the purpose of the goods or services in terms of how effectively it will perform. Performance is a logical extension of function. Performance specifications define the task or desired result by focusing on what is to be achieved. They do not describe the method of achieving the desired result.2. Technical (or conformance) specificationsThese are Specifications that define the technical and physical characteristics and/or measurements of a product, such as physical aspects (e.g. dimensions, colour, and surface finish), design details, material properties, energy requirements, processes, maintenance requirements and operational requirements. They are used when functional and performance characteristics are insufficient to define the requirement and are often used for engineering and information technology requirements.
- Specification Writing- CIPS study guide page 9-11 LO 1, AC 1.1
Southwark is negotiating a contract with Orchard to provide software and IT services. Orchard will manufacture and install the products which are contractually supplied by IBM. Southwark's procurement manager is worried that during the contract there would be some problems that they would not able to claim for damages from Orchard. Which of the following should be included in the head contract so that Southward can sue IBM, should the need arise?
Answer(s): C
A Collateral Warranty is a contract under which a consultant, a building contractor or a sub- contractor warrants to a third party that is has fulfilled its obligations under its professional appointment, building contract or sub-contract. The purpose of a Collateral Warranty is to give a third party, who is not a party to the original contract, rights to enforce that original contract. In this case, IBM is the subcontractor, then purchaser can use collateral warranty deed to bind them.
- Collateral Warranties an Overview- CIPS study guide page 39-40 LO 1, AC 1.2
Danielle buys a car from Aaron. Not long after, she receives an proposal from Brian, who is interested in buying the car but his budget is very constraint. Then, Brian decides to sign a hire purchase agreement with Danielle which lasts 4 years. Brian lives very far from Danielle, so he hires Charlie to deliver the car to his place. During the transport, Charlie has an accident and the car is written off. At the time of accident, who has the title of the car?
Hire purchase is an arrangement for buying expensive consumer goods, where the buyer makes an initial down payment and pays the balance plus interest in installments. The ownership of the merchandise is not officially transferred to the buyer until all the payments have been made. Danielle has purchased the car from Aaron, which means its title has been transferred to her. The accident happens before the last instalment is paid. Therefore, the ownership of the car still belongs to Danielle
CIPS study guide page 70 LO 1, AC 1.3
In a contract, both buyer and supplier agreed the lead time is 3 days. The contract also requires that any variation must be made in writing. Then the buyer places an order by phone call and requests delivery the next day, but the supplier delivers on the third day since the order. Can buyer refuse to pay as supplier did not deliver per time?
Answer(s): A
Lead time is the amount of time that passes from the start of a process until its conclusion. In procurement, lead time can be understood as the amount of time that passes from placing an order until the delivery.In the scenario, the contract requires the supplier to make a delivery within 3 days since the order. This contract can only be amended with written consent from both parties. Therefore, there is no ground for shortening the lead time to 1 day because the new lead time is only the request of buyer. Then the supplier still makes delivery within agreed lead time. LO 1, AC 1.1