Which of the following is a root cause of 'resource allocation syndrome'?

  1. not enough resource is available to complete several projects at once
  2. resources are underused
  3. team members do not wish to finish projects
  4. lack of funding for projects

Answer(s): A

Explanation:

Resource allocation syndrome, as described by Engwall and Jerbrant, occurs when multiple projects compete for limited resources in multi-project environments. The shortage leads to delays and conflicts between project teams.


Reference:

CIPS L5M8 Study Guide, p.48.



Michael is the head of the Steering Committee at ABC Consultancy and must allocate resources to several projects. One project is suffering delays due to lack of staff. Should Michael reallocate resources to this project?

  1. yes ­ resources should always be allocated depending on timescales
  2. yes ­ all resources should be diverted to this project until it is complete
  3. no ­ this may increase competition and animosity between project teams
  4. no ­ delays are always unavoidable in project management

Answer(s): C

Explanation:

The guide advises against diverting resources to one delayed project, as this can create competition and resentment across teams and may cause a domino effect of further delays. Balanced prioritisation is required.


Reference:

CIPS L5M8 Study Guide, p.49.



The Critical Chain Methodology of project management removes what from a project in order to improve efficiencies?

  1. redundant resources including personnel
  2. buffer time in task stages
  3. budget constraints
  4. number of tasks

Answer(s): B

Explanation:

Critical Chain Project Management (CCPM) eliminates individual task safety buffers, consolidating them into a single project buffer to reduce delays and improve efficiency.


Reference:

CIPS L5M8 Study Guide, pp.58­61.



In the project lifecycle, which of the following stages is completed last?

  1. control
  2. co-ordination
  3. closure
  4. review

Answer(s): D

Explanation:

The final step in the lifecycle is the review stage, following closure. It evaluates project success against objectives and captures lessons learned for future improvement.


Reference:

CIPS L5M8 Study Guide, p.66.



Yes Ltd is a consultancy organisation running many projects simultaneously. Fiona, the CEO, claims that all projects should use project management software. Is this correct?

  1. yes ­ software will ensure projects are delivered to timescales and budgets
  2. yes ­ all projects require the use of software to track data
  3. no ­ the use of software may not be required for smaller projects
  4. no ­ software should never be used as a project management tool

Answer(s): C

Explanation:

The guide explains that software should only be used if it adds value to project control and efficiency. For small, low-complexity projects, it might be unnecessary or uneconomical.


Reference:

CIPS L5M8 Study Guide, p.71.



Viewing page 7 of 19
Viewing questions 31 - 35 out of 88 questions


Post your Comments and Discuss CIPS L5M8 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!