A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?

  1. Escalate the communication issues.
  2. Implement a communication platform.
  3. Review the communication plan.
  4. Talk with the head of the PMO.

Answer(s): C



An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?

  1. The ticket system provided access by default without any approval.
  2. The project manager did not perform proper project planning.
  3. The system is lacking proper access controls.
  4. Sensitive data was incorrectly classified during the audit process.

Answer(s): C



An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens’ complaints. Which of the following solutions would be BEST?

  1. Enterprise resource planning and end user applications
  2. Electronic document and record management systems
  3. Customer relationship management and databases
  4. Content management and financial systems

Answer(s): B



A system was implemented, and testing was successfully completed. Which of the following should the project manager do NEXT?

  1. Validate against the scope statement and ask for sign-off.
  2. Run a control chart to ensure the quality of the deliverables.
  3. Review the risk register and close up residual risks.
  4. Start the training and handoff for the operations team.

Answer(s): A



Page 20 of 53



Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

samsam commented on September 11, 2024
i hope this will help me pass
Anonymous
upvote

Joe commented on March 26, 2024
it helped me pass
Anonymous
upvote