During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT?
Answer(s): B
Project A and Project B share a team member. The team member is falling behind on a task for Project B. Which of the following is the BEST action to take to get the task for Project B back on track?
Answer(s): A
A portfolio manager needs to provide the senior management team with a dynamic, high-level, monthly status update on all active projects in the portfolio. Which of the following should the manager use to accomplish this task?
A project manager has been assigned to a project that involves replacing key operational equipment. The project manager is new to the industry and has learned that compliance requirements must be met. Which of the following should the project manager do FIRST?
Answer(s): C
Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:
Jack commented on October 18, 2024 are these legit ? Anonymous upvote
samsam commented on September 11, 2024 i hope this will help me pass Anonymous upvote
Joe commented on March 26, 2024 it helped me pass Anonymous upvote
Our website is free, but we have to fight against bots and content theft. We're sorry for the inconvenience caused by these security measures. You can access the rest of the PK0-005 content, but please register or login to continue.