Free D-VXB-DY-A-24 Exam Braindumps (page: 5)

Page 4 of 20

Who is responsible for raising the Internal Assessment (IA) during an RCM upgrade?

  1. RCM Lead
  2. Project Manager
  3. Implementation Specialist
  4. District Manager

Answer(s): A

Explanation:

Review the RCM Upgrade Process: The RCM (Release Certification Matrix) upgrade process involves a series of steps to ensure that the VxBlock system is updated according to Dell EMC's standards. Identify the Role of the RCM Lead: The RCM Lead is typically responsible for overseeing the RCM upgrade process, which includes raising the Internal Assessment (IA) to ensure that all components are compliant with the latest RCM standards.
Understand the Importance of IA: The Internal Assessment is a critical part of the RCM upgrade process. It helps identify any potential issues that might affect the upgrade and ensures that the system is ready for the new RCM1.
Acknowledge the Responsibilities: While the Project Manager, Implementation Specialist, and District Manager may have roles in the RCM upgrade process, it is the RCM Lead who is specifically responsible for raising the IA as part of their duties.





Refer to the exhibit.

A cable with the following label was connected to the wrong equipment type:

* M91A-01:01 U61A-01:09

Based on the exhibit, what is the target equipment type?

  1. Nexus 9xxx, Slot A, Port1
  2. UCS 5108 Chasses A, Slot 1, Port 9
  3. MDS 9xxx, Slot 1, Port 1
  4. UCS 6xxx FI, Uplink A, Slot 1, port 9

Answer(s): C

Explanation:

The label on the cable indicates two parts: "M91A-01:01" and "U61A-01:09". The first part of the label "M91A" refers to a specific type of equipment as per the exhibit. According to the exhibit, "M9" corresponds to "MDS 9xxx", which is a Cisco Multilayer Director Switch. The second part of the label, "U61A", does not directly match any category in the provided list; however, it seems to be an internal reference that could be related to user-specific configurations or locations. Since we are looking for the target equipment type and not where it was mistakenly connected, we focus on the first part of the cable label. The numbers following "M91A" indicate slot and port information. Therefore, based on this labeling system and referring to the exhibit provided, which lists various EMC and Cisco equipment types along with their corresponding codes (like AP for APIC Appliance or CN for Cust. Network), we can deduce that "M91A" stands for "MDS 9xxx". The subsequent numbers "-01:01" suggest Slot 1, Port 1.



DRAG DROP (Drag and Drop is not supported)
In the Enhanced Knowledge Transfer Phase, what is the correct sequence of steps in the Finalize Project Deliverables?

  1. See Explanation section for answer.

Answer(s): A

Explanation:

Cleanup and Run Backups
Update Checklist
Complete Project Documentation

Generate SCR (Service Change Request)
Provide Documentation

In the Enhanced Knowledge Transfer Phase, the sequence of steps to finalize project deliverables ensures that all necessary tasks are completed in an orderly and efficient manner. Here's a detailed breakdown:
Cleanup and Run Backups:
This step involves ensuring that the system and data are clean and backed up. It's crucial to clean up any temporary files or unnecessary data and perform backups to safeguard against data loss.


Reference:

Best practices in project management emphasize the importance of securing data before concluding the project.

Update Checklist:



DRAG DROP (Drag and Drop is not supported)
Based on the Dell EMC RCM Workbook upgrade plan, in what sequence should VxBlock components be upgraded?

  1. See Explanation section for answer.

Answer(s): A

Explanation:

VxBlock Central
Network
Storage
Compute
Virtualization

In the Dell EMC RCM (Release Certification Matrix) Workbook upgrade plan, the sequence of upgrading VxBlock components is designed to ensure system stability and minimize disruptions. Here's the detailed reasoning for the correct sequence:
VxBlock Central:
VxBlock Central is the management and orchestration layer of the VxBlock system.

Upgrading this first ensures that the management tools are compatible with the new versions of the other components and can properly coordinate and monitor the upgrade process.


Reference:

Dell EMC documentation emphasizes upgrading management and orchestration tools first to ensure compatibility and support for subsequent upgrades.
Network: