Free DES-4421 Exam Braindumps
Specialist - Implementation Engineer, PowerEdge MX Modular Exam Questions 11–15 (page: 4)

Updated On: 9-Feb-2026

What is a valid option when resetting iDRAC to factory defaults?

  1. Preserve user and network settings
  2. Preserve network and storage settings
  3. Preserve identity and network settings
  4. Preserve storage and user settings

Answer(s): A


Reference:

https://www.dell.com/support/manuals/us/en/04/poweredge-r740/idrac_3.21.21.21_ug/reset-idrac-and-reset-idrac-to-default?guid=guid-1b5c2d57-05c8-4098-8344-49c984839c30&lang=en-us



What is a characteristic of MX7000 networking in Full Switch Mode?

  1. Layer 2 bridging is disabled by default and interfaces must join a bridge domain (VLAN) before being able to forward frames.
  2. Networking is enabled by default and all switch-specific OS10EE capabilities are available.
  3. Networking is available on MX9116n FSE and MX7116n FEM but not on the MX5108n.
  4. Switches operate as layer 2 I/O aggregation devices and are managed through OME-M.

Answer(s): B


Reference:

https://infohub.delltechnologies.com/l/test2-poweredge-mx-networking-architecture-guide-1/operating-modes-description-7



In an MX7000, which components are cooled by the rear fans?

  1. Fabric A, B, and C IOMs only
  2. All compute and storage sleds
  3. Management Modules only
  4. Fabric A, B, and C IOMs and the Management Modules

Answer(s): D


Reference:

http://bladesmadesimple.com/2018/08/a-first-look-at-the-dell-emc-poweredge-mx/



A datacenter administrator has been tasked to perform firmware updates of the whole chassis and its components based on the latest dell.com catalog.
What is the correct sequence of actions?

Select and Place:

Exhibit A:



Exhibit B:

  1. Please refer to Exhibit B for the answer.

Answer(s): A



The MDB chassis tub assembly vertical distribution board provides connectivity to which chassis components?

  1. Five near fan modules
  2. Four cooling fans and four fabric I/O modules
  3. Power supplies, compute sleds, Management Modules, and two fabric I/O modules
  4. Pear power supplies, compute sleds, Management Modules, and all fabric I/O modules

Answer(s): B


Reference:

https://i.dell.com/sites/csdocuments/Product_Docs/en/dell_emc_poweredge_mx7000_technical_guide.pdf



Viewing page 4 of 12
Viewing questions 16 - 20 out of 54 questions


Post your Comments and Discuss EMC DES-4421 exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!