After the creation of the Release Plan, the Product Owner says:
Over the next four months with eights two-week Sprints we will complete exactly 240 Story Points of work.
The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.
What are the other two factors?

  1. Changed requirements and estimation mode
  2. Changed requirements and revised estimates
  3. Fixed requirements and estimation mode
  4. Fixed requirements and revised estimates

Answer(s): B



"As a coach, I can manage information about swimmers on my team." What would be a good technique to split the above User Story into smaller stories?

  1. Do not split. The User Story is small enough
  2. Splitting the User Story into Epics
  3. Splitting the User Story into separate CRUD operations
  4. Splitting the User Story into tasks

Answer(s): C



A Sprint planning is created in a Sprint Planning meeting. Anyone involved in taking a raw idea and turning it into a functioning product should be present in this meeting.
Who acts as the facilitator for this meeting?

  1. An Analyst
  2. The Product Owner
  3. The Project Manager
  4. The scrum Master

Answer(s): B



Sprint planning should result in a commitment on what will be delivered at the end of the Sprint.
Who makes this commitment?

  1. The Product Owner
  2. The Scrum Master
  3. The team

Answer(s): C