Which one of the following is NOT a type of identified dependencies in a Scrum project?

  1. Critical
  2. Mandatory
  3. Discretionary
  4. Internal

Answer(s): A


Reference:

http://blog.scrumstudy.com/dependency-determination-in-scrum-project/



Which one of the following statements about the history of Scrum is NOT correct?

  1. The idea of Scrum was derived from a "rugby" approach, in which "a team tries to go the distance as a unit,
    passing the ball back and forth."
  2. Takeuchi and Nonaka proposed that product development should be like a sequential relay race.
  3. Scrum was based on a flexible and all-inclusive product development strategy where the development team works as a unit to reach a common goal.
  4. Takeuchi and Nonaka based their approach on manufacturing case studies from various industries.

Answer(s): B

Explanation:

:
Takeuchi and Nonaka proposed that product development should not be like a sequential relay race, but rather should be analogous to the game of rugby where the team works together, passing the ball back and forth as they move as a unit down the field. The rugby concept of a "Scrum" (where a group of players form together to restart the game) was introduced in this article to describe the authors' proposal that product development should involve "moving the Scrum downfield".


Reference:

http://blog.scrumstudy.com/the-story-behind-origin-of-scrum/



Which of the following statements about Release Planning Session is/are Correct? A) Release Planning Sessions are conducted to develop a plan that defines when various sets of usable functionality or products will be delivered to the customer. B) Release Planning Sessions enable the Scrum Team to have an overview of the releases and delivery schedule for the product they are developing.
C) Whether the releases will follow a phased deployment pattern or a continuous deployment pattern depends on the stakeholder requirements.
D) Release Planning Sessions should produce a detailed Release Plan for the entire project.

  1. A
  2. A and
  3. and
  4. A and D

Answer(s): B

Explanation:

:
Release Planning Sessions are conducted to develop a Release Plan. The plan defines when various sets of usable functionality or products will be delivered to the customer. In Scrum, the major objective of a Release
Planning Meeting is to enable the Scrum Team to have an overview of the releases and delivery schedule for the product they are developing so that they can align with the expectations of the Product Owner and relevant stakeholders (primarily the project sponsor).


Reference:

http://blog.scrumstudy.com/release-planning-sessions-in-scrum/



The Scrum Team along with the Scrum Master adopted the Fist of Five technique to arrive at accurate estimations for the prioritized User Stories. The results of the vote of each team member are as follows: three members: 2 fingers; four members: 3 fingers; and two members: 5 fingers.
Which of the following options is in plurality?

  1. I am not sure and would like to go with the group's consensus conclusion.
  2. I agree with the group's conclusion and would like to discuss some minor issues.
  3. I disagree with the group's conclusion and have major concerns.
  4. I wholeheartedly agree with the group's conclusion.

Answer(s): C


Reference:

https://ryanripley.com/5-reasons-a-scrum-master-should-use-fist-of-five-voting/