Peter is a Scrum Master on a software development project for a premier chain of hospitals. It is his responsibility to conduct Daily Standups.
Which of the following is not a

  1. Option A
  2. Option B
  3. Option C
  4. Option D

Answer(s): D



Team during the Daily Standups?

  1. What will I work on today?
  2. What did I complete yesterday?
  3. Am I facing any impediments or obstacles?
  4. How will I solve the impediments that I am facing?

Answer(s): D


Reference:

https://www.mountaingoatsoftware.com/agile/scrum/meetings/daily-scrum



Which of the following statements on Risk Management in a Scrum project is INCORRECT?

  1. The iterative nature of Scrum with its rapid turnaround time and feedback cycles allows for early detection of failures.
  2. Risks can be managed only at the project level, even if they are related to or originate in portfolios or programs.
  3. Risk Burndown Charts aye an important tool for communicating information related to risks to the Stakeholders.
  4. Risk is largely minimized in Scrum due to the flexibility in adding or modifying requirements at any time in the project lifecycle.

Answer(s): B


Reference:

http://blog.scrumstudy.com/how-scrum-framework-minimizes-risks-threats-in-projects- 2/



Which of the following is a responsibility of the Scrum Master in the context of change in Scrum?

  1. Eliminating all changes that may affect the quality of deliverables and processes
  2. Facilitating identification of Change Requests by the Scrum Team and their assessment and prioritization by the Product Owner.
  3. Providing requests for changes in a project.
  4. Approving changes that are amended, removed, or added according to project requirements, and communicating the same to the Scrum Team.

Answer(s): B