Free ASM Exam Braindumps (page: 8)

Page 7 of 58

A team's physical environment can have a big influence on how Agile a team can become. An important benefit of an open space workplace is the ease with which the layout of the area can be changed.
Why does this comply with the Agile principles?

  1. It follows the inspect and adapt cycle, as the people on the team are learning how to work best with one another during the process.
  2. Pair programming is only possible in an open environment.
  3. Self-organization is only possible in an open space environment.
  4. With people involved, there will always be people issues. Open work spaces allow the Scrum Master to detect people issues and resolve them.

Answer(s): C



Company ABC always works in the following way: The business chooses a set of requirements that it believes will add business value. It communicates the requirements to the IT organization. The IT organization responds back with a plan and estimates of cost and schedule. The business agrees to that plan. The IT organization executes the plan and delivers a product to the business.
What type of framework is company ABC following?

  1. DevOps
  2. DSDM
  3. Lean
  4. Waterfall

Answer(s): B



A Development Team consists of various different roles: analysts, programmers, UX experts, DBA and systems architects. They are estimating Backlog Items in Ideal Days.
What is the best approach to provide estimates for the Backlog Items?

  1. Each role should provide a separate estimate; the Scrum Master integrates them.
  2. Ideal days' estimation is not feasible in this case; Story Points should be used.
  3. The Development Team provides a single estimate for each Backlog Item.
  4. The Product Owner will integrate the input on the estimates from each role.

Answer(s): C



Inexperienced Agile teams tend to overestimate how much they will achieve in the first Sprint.
Which project management activity will be most important in this case?

  1. Determine the Velocity of the Team and plan accordingly
  2. Use Planning Poker to get a reliable estimate
  3. Use Stakeholder Management to manage expectations

Answer(s): C






Post your Comments and Discuss EXIN ASM exam with other Community members: