Which two of the following are the key expected results of a quality management system that conforms to the requirements of ISO 9001:2015?

  1. Decreased number of nonconforming products in all stages of the manufacturing cycle
  2. Decreased number of management system nonconformities
  3. Consistently provide products that meet customers' requirements
  4. Increased profits
  5. Decreased number of warranty claims
  6. Enhanced customer satisfaction

Answer(s): C,F

Explanation:

According to the ISO 9001:2015 document, the key expected results of a quality management system that conforms to the requirements of ISO 9001:2015 are:
· the ability to consistently provide products and services that meet customer and applicable statutory and regulatory requirements;
· the enhancement of customer satisfaction.
These results are derived from the quality management principles of customer focus and process approach, which are the basis of the ISO 9000 family of standards1. Customer focus means understanding and meeting customer needs and expectations, as well as exceeding them when possible1. Process approach means managing activities as interrelated processes that function as a coherent system, which leads to consistent and predictable results1.
Therefore, the correct answer is C and F.


Reference:

2: ISO 9001:2015 - Quality management systems -- Requirements 1: ISO - Quality management principles



Which two of the following aspects of a quality management system must the organisation continually improve?

  1. Suitability
  2. Adaptability
  3. Effectiveness
  4. Responsiveness
  5. Efficiency
  6. Applicability

Answer(s): C,E

Explanation:

According to the ISO 9001:2015 document, the organisation must continually improve the suitability, adequacy, and effectiveness of the quality management system1. However, among the six options given, only effectiveness is directly mentioned as an aspect of the quality management system that must be continually improved. Therefore, C is one of the correct answers. Efficiency, on the other hand, is not explicitly stated as an aspect of the quality management system that must be continually improved, but it is implied by the quality management principle of improvement, which states that successful organisations have an ongoing focus on improvement2. One of the key benefits of applying this principle is improving operational effectiveness and efficiency2. Therefore, E is another correct answer.
Suitability, adaptability, responsiveness, and applicability are not aspects of the quality management system that must be continually improved, according to the ISO 9001:2015 document. They may be related to the quality management system, but they are not the focus of continual improvement.
Therefore, the correct answer is C and E.


Reference:

1:ISO 9001:2015 - Quality management systems -- Requirements 2: ISO - Quality management principles



DRAG DROP (Drag and Drop is not supported)
Put the following steps of a third-party audit into the correct sequence in which they happen.

  1. See Explanation section for answer.

Answer(s): A

Explanation:

Sequence:
Stage 1 Audit
Stage 2 Opening Meeting
Interviews
Stage 2 Closing Meeting
Close-out of Stage 2 Audit Findings
Issue Certificate
Surveillance Audit
Follow-up Audit
To complete the sequence, you can drag and drop the options to the appropriate blank section.
Here is a brief explanation of each step:
Stage 1 Audit: This is the initial audit that aims to assess the readiness of the organization for the stage 2 audit. It involves reviewing the documentation of the quality management system, evaluating the scope and objectives of the audit, and identifying any major gaps or nonconformities34.
Stage 2 Opening Meeting: This is the meeting that marks the start of the stage 2 audit. It involves confirming the audit plan, the audit criteria, the audit scope, and the audit team. It also provides an opportunity for the auditee to ask any questions or raise any concerns34. Interviews: This is the main activity of the stage 2 audit, where the audit team collects evidence by interviewing the personnel involved in the quality management system, observing the processes and activities, and examining the records and documents. The audit team uses various techniques, such as sampling, measurement, analysis, and evaluation, to verify the conformity and effectiveness of the quality management system345.
Stage 2 Closing Meeting: This is the meeting that marks the end of the stage 2 audit. It involves presenting the audit findings, the audit conclusions, and the audit report to the auditee. It also provides an opportunity for the auditee to provide feedback, ask questions, or dispute any findings34.
Close-out of Stage 2 Audit Findings: This is the process of verifying that the auditee has taken appropriate corrective actions to address any nonconformities or opportunities for improvement identified during the stage 2 audit. The audit team may request evidence or conduct a follow-up visit to confirm the effectiveness of the corrective actions34.
Issue Certificate: This is the process of issuing a certificate of conformity to the auditee, if the audit team is satisfied that the quality management system meets the requirements of the standard and that there are no major nonconformities or unresolved issues. The certificate is valid for a specified period, usually three years, and is subject to periodic surveillance audits34. Surveillance Audit: This is the process of conducting periodic audits, usually once a year, to monitor the continued conformity and effectiveness of the quality management system. It involves reviewing the changes, improvements, and performance of the quality management system, and identifying any new nonconformities or opportunities for improvement34.
Follow-up Audit: This is the process of conducting an additional audit, usually in response to a significant change, a complaint, or a major nonconformity, to verify the impact and the corrective actions taken by the auditee. It may result in the suspension, withdrawal, or renewal of the certificate, depending on the outcome of the audit34.



According to ISO 19011, what two activities take place during the conduct of a audit follow-up?

  1. Verify the effectiveness of the implemented corrective actions
  2. Verify corrections taken to fix the reported non-conformities
  3. Verify legal compliance
  4. Plan the next audit
  5. Determine feasibility of the audit
  6. Assign roles and responsibilities of observers

Answer(s): A,B

Explanation:

According to ISO 19011:2018, clause 6.7, the audit follow-up is the process of verifying the completion and effectiveness of corrective actions taken by the auditee as a result of an audit. The audit follow-up can include two main activities:
Verifying the effectiveness of the implemented corrective actions: this means checking whether the actions taken by the auditee have addressed the root causes of the nonconformities and prevented their recurrence or occurrence in other areas. The verification can be done by reviewing documents, records, data, or other evidence provided by the auditee, or by conducting a follow-up audit on site or remotely.
Verifying corrections taken to fix the reported non-conformities: this means checking whether the auditee has corrected the nonconformities identified during the audit and eliminated their immediate effects. The verification can be done by reviewing documents, records, data, or other evidence provided by the auditee, or by conducting a follow-up audit on site or remotely. The audit follow-up can be conducted as a separate audit or as part of a subsequent audit, depending on the audit programme, the audit objectives, the audit criteria, the audit scope, the audit risks, and the audit findings. The audit follow-up should be planned and conducted in accordance with the same principles and processes as the initial audit, and the results should be documented and reported accordingly.


Reference:

ISO 19011:2018(en), Guidelines for auditing management systems, clause 6.7 ISO 19011 Management Systems Audit Checklist | Process Street, task 6.7.1 and 6.7.2

Conducting the Audit Follow-Up: When to Verify - The Auditor, section "Conducting the audit follow- up"



Page 2 of 29



Post your Comments and Discuss EXIN ISO-9001-Lead-Auditor exam with other Community members:

Inbarajan commented on January 02, 2025
Very useful
Anonymous
upvote

Faith Egwuenu commented on December 09, 2024
The case studies/questions were very helpful.
Anonymous
upvote

Md. Jakir Hossain commented on November 17, 2024
pls help me given total question
BANGLADESH
upvote

Joseph commented on November 08, 2024
The questions and answers/explanations are very helpful and professional, thank you
Anonymous
upvote

Tadele commented on November 02, 2024
Help full to next exam
Anonymous
upvote

Arvind Sharma commented on October 27, 2024
Helpful questions for preparation foe LA exam
Anonymous
upvote

Rajesh Kumar M - commented on October 26, 2024
For the question 6- the continual improvement , the organization shall continually improve the suitability, adequacy and effectiveness of the QMS. Not Efficiency, Refer Clause 10.3 continual improvement in ISO 9001 :2015
Anonymous
upvote

jakir commented on October 24, 2024
its really more help full.
BANGLADESH
upvote

Apvj commented on October 17, 2024
Need to update section 5 questions,it was all new question today in exam , unitl section 4 it was fine even though pattern of question changed
Anonymous
upvote

vaibgav commented on October 13, 2024
nice paper for practise
Anonymous
upvote

Md Nur Hosen commented on September 21, 2024
Preparing for exam
Anonymous
upvote

SRILANKA commented on September 04, 2024
PREPARING FOR EXAM
Anonymous
upvote