Free ISO-9001-Lead-Auditor Exam Braindumps (page: 4)

Page 4 of 29

You are conducting a third-party Stage 1 audit at ABC Ltd, a single-site organisation that manufactures wooden furniture. You interview the Technical Director to learn more about the organisation. The Technical Director explains that they have had a successful year and that obtaining ISO 9001 certification will support the further growth of the business. You ask for an overview of the organisation's structure and its interrelationships with external interested parties.

The Technical Director shows you a document detailing all business processes and interrelationships. You notice in this document that another organisation called Teak Ltd manufactures wooden furniture on behalf of ABC Ltd. The Technical Director confirms this capability has been accounted for in the scope of the quality management system. You learn that the furniture manufactured by Teak Ltd has accounted for 40% of the sales revenue over the previous 12 months.

Which two of the following options best describe how you would plan the audit of the interrelationship with Teak Ltd during the Stage 2 audit at ABC Ltd?

  1. Verify Teak Ltd supply arrangements as described in the ABC Ltd quality management system
  2. Verify if Teak Ltd are certified to ISO 9001
  3. Verify the controls concerning customer property implemented by Teak Ltd
  4. Verify how ABC Ltd evaluates the performance of Teak Ltd
  5. Verify the quality management system at Teak Ltd by conducting an audit at their site
  6. Verify whether the design processes of Teak Ltd comply with ISO 9001

Answer(s): A,D

Explanation:

According to ISO 9001:2015, clause 8.4, an organization is required to control the processes, products and services provided by external providers, including those that affect the quality of the organization's own products and services. This includes determining the controls to be applied to the external provision of processes, products and services, as well as the information to be communicated to the external providers. The organization is also required to monitor, measure, and evaluate the performance of the external providers and retain documented information of these activities.
Therefore, in the scenario given, ABC Ltd is responsible for controlling the processes, products and services provided by Teak Ltd, as they affect the quality of ABC Ltd's own products and services. This means that ABC Ltd should have established criteria and methods for evaluating the performance of Teak Ltd, as well as documented information of the results of such evaluation. ABC Ltd should also have defined the supply arrangements with Teak Ltd, including the specifications, requirements, and verification activities related to the products and services provided by Teak Ltd. Hence, the best options to describe how to plan the audit of the interrelationship with Teak Ltd during the Stage 2 audit at ABC Ltd are A and D, as they are aligned with the requirements of ISO 9001:2015, clause 8.4. The other options are either irrelevant or beyond the scope of the audit, as they do not pertain to the control of external provision by ABC Ltd.


Reference:

ISO 9001:2015(en), Quality management systems -- Requirements, clause 8.4 ISO 19011:2018(en), Guidelines for auditing management systems, clause 6.3.1 and 6.4.2 ISO 9001 Lead Auditor Training Course | IRCA Certified | BSI, section "Learning objectives" ISO 9001 Lead Auditor Course Material | 3FOLD Education Centre, module 5 and 6



Which two of the following should be included in an audit plan?

  1. List of findings from the last audit
  2. Name of the auditee general manager
  3. Signature of Certification Body Technical Reviewer
  4. Sequence and timings of audit activities
  5. Date of next audit
  6. Name of auditees and auditors

Answer(s): D,F

Explanation:

According to ISO 19011:2018, clause 6.3.2, an audit plan should include the following information:
The audit objectives, scope, and criteria
The audit team members and their roles and responsibilities
The audit schedule, including the sequence and timings of audit activities, such as opening meeting, document review, interviews, observations, closing meeting, etc. The expected time and duration of each audit activity and location The name and contact details of the auditee's representative and other relevant parties The allocation of appropriate resources to support the audit activities

The audit methods and techniques to be used, such as interviews, observations, sampling, etc.
The audit documents and records to be prepared and retained
The audit language and communication methods
The audit risks and opportunities and how to address them
The audit follow-up arrangements, if applicable
Therefore, the correct answer is D and F, as they are essential elements of an audit plan. The other options are either irrelevant or optional for an audit plan.


Reference:

ISO 19011:2018(en), Guidelines for auditing management systems, clause 6.3.2 ISO 19011: Guidelines for Auditing Management Systems | ASQ, section "Making audit arrangements"
ISO 19011 Management Systems Audit Checklist | Process Street, task 6.3.2



DRAG DROP (Drag and Drop is not supported)
The following are stages of an audit, put them in the order they would be conducted.

  1. See Explanation section for answer.

Answer(s): A

Explanation:



Establishing the audit programme objectives
Determining and evaluating the audit programme risks and opportunities Establishing the audit programme
Initiating the audit

Preparing all audit activity
Conducting the audit activities
To complete the sequence, you can drag and drop the options to the appropriate blank section.
Here is a brief explanation of each stage:
Establishing the audit programme objectives: This is the first stage of the audit process, where the purpose, scope, and criteria of the audit programme are defined. The audit programme objectives should be aligned with the strategic direction and policies of the organization, and should address the needs and expectations of the interested parties12.
Determining and evaluating the audit programme risks and opportunities: This is the second stage of the audit process, where the factors that can affect the achievement of the audit programme objectives are identified and assessed. The audit programme risks and opportunities should consider the internal and external issues, the requirements and changes of the interested parties, and the results and feedback from previous audits12.
Establishing the audit programme: This is the third stage of the audit process, where the audit programme is designed and implemented. The audit programme should include the audit programme procedures, the audit programme resources, the audit methods and techniques, the audit frequency and schedule, and the audit programme performance indicators12. Initiating the audit: This is the fourth stage of the audit process, where the audit is prepared and planned. The audit initiation involves selecting the audit team, establishing the contact with the auditee, defining the audit objectives, scope, and criteria, developing the audit plan, and conducting the document review123.
Preparing all audit activity: This is the fifth stage of the audit process, where the audit activities are organized and coordinated. The audit preparation involves assigning the audit tasks, communicating with the auditee and the audit team, arranging the logistics, preparing the working documents, and conducting the opening meeting123.
Conducting the audit activities: This is the sixth and final stage of the audit process, where the audit evidence is collected and evaluated. The audit conduct involves performing the audit activities, such as interviews, observations, document reviews, and tests, documenting the audit findings, preparing the audit conclusions, and conducting the closing meeting123.
I hope this helps you with your ISO 9001 Lead Auditor objectives and content. If you have any further questions, please feel free to ask.


Reference:

1:ISO 19011:2018 - Guidelines for auditing management systems 2: Audit Process | Flowchart | Summary - Accountinguide 3: What are the Stages of the Auditing Process & Why it is Important ...



You work for organisation

  1. You are asked to lead an internal audit of A's quality management system. It has a head office in Plant A1 and a second Plant A2 nearby. Due to the COVID-19 pandemic, production in A2 was discontinued and it was rented to a logistics organisation B, not related to There are no A employees working in A2. Organisation A expects to reassume production in A2 as soon as possible.
    Which of the following actions would you consider appropriate when planning the internal audit of A's quality management system?
  2. Visit Plant A2 to interview personnel of company B
  3. Visit Plant A2 to interview B's quality manager
  4. Visit Plant A2 to interview A's security personnel and B's maintenance department
  5. Interview the A2 plant manager, now working in Plant A1

Answer(s): D

Explanation:

In this scenario, the organisation A has two plants, A1 and A2, but the production in A2 was discontinued due to the COVID-19 pandemic and the plant was rented to another organisation B. There are no A employees working in A2, and the organisation A expects to reassume production in A2 as soon as possible. Therefore, the appropriate action to plan the internal audit of A's quality management system is:
· Interview the A2 plant manager, now working in Plant A1: This action involves interviewing the person who is responsible for the management and operation of the plant A2, and who is currently working in the plant A1. The interview should aim to gather information about the status and condition of the plant A2, the impact of the COVID-19 pandemic on the quality management system, the arrangements and agreements with the organisation B, and the plans and actions to resume production in the plant A25 . This action is relevant and necessary for the internal audit, as it can help to assess the readiness and effectiveness of the quality management system, and to identify any gaps or nonconformities that need to be addressed.
The other options are not appropriate actions to plan the internal audit of A's quality management system, according to the web search results from my internal tool. They are:
· Visit Plant A2 to interview personnel of company B: This action involves visiting the plant A2 and interviewing the personnel of the organisation B, who are not related to the organisation A and who are not part of the quality management system. This action is irrelevant and unnecessary for the internal audit, as it can not provide any evidence or information about the conformity and improvement of the quality management system of the organisation A5 . · Visit Plant A2 to interview B's quality manager: This action involves visiting the plant A2 and interviewing the quality manager of the organisation B, who is not related to the organisation A and who is not part of the quality management system. This action is irrelevant and unnecessary for the internal audit, as it can not provide any evidence or information about the conformity and improvement of the quality management system of the organisation A5 . · Visit Plant A2 to interview A's security personnel and B's maintenance department: This action involves visiting the plant A2 and interviewing the security personnel of the organisation A and the maintenance department of the organisation B, who are not directly involved in the quality management system. This action is irrelevant and unnecessary for the internal audit, as it can not provide any evidence or information about the conformity and improvement of the quality management system of the organisation A5 .
Therefore, the correct answer is D.


Reference:

1:Quality audit - Wikipedia 2: A step-by-step guide to internal quality audits 3: ISO 9001:2015 - Quality management systems -- Requirements 4: ISO 19011:2018 - Guidelines for auditing management systems 5: Audit Process | Flowchart | Summary - Accountinguide : What are the Stages of the Auditing Process & Why it is Important ...



Page 4 of 29



Post your Comments and Discuss EXIN ISO-9001-Lead-Auditor exam with other Community members:

Inbarajan commented on January 02, 2025
Very useful
Anonymous
upvote

Faith Egwuenu commented on December 09, 2024
The case studies/questions were very helpful.
Anonymous
upvote

Md. Jakir Hossain commented on November 17, 2024
pls help me given total question
BANGLADESH
upvote

Joseph commented on November 08, 2024
The questions and answers/explanations are very helpful and professional, thank you
Anonymous
upvote

Tadele commented on November 02, 2024
Help full to next exam
Anonymous
upvote

Arvind Sharma commented on October 27, 2024
Helpful questions for preparation foe LA exam
Anonymous
upvote

Rajesh Kumar M - commented on October 26, 2024
For the question 6- the continual improvement , the organization shall continually improve the suitability, adequacy and effectiveness of the QMS. Not Efficiency, Refer Clause 10.3 continual improvement in ISO 9001 :2015
Anonymous
upvote

jakir commented on October 24, 2024
its really more help full.
BANGLADESH
upvote

Apvj commented on October 17, 2024
Need to update section 5 questions,it was all new question today in exam , unitl section 4 it was fine even though pattern of question changed
Anonymous
upvote

vaibgav commented on October 13, 2024
nice paper for practise
Anonymous
upvote

Md Nur Hosen commented on September 21, 2024
Preparing for exam
Anonymous
upvote

SRILANKA commented on September 04, 2024
PREPARING FOR EXAM
Anonymous
upvote