Which is NOT a typical Key Performance Indicator which can be used to measure the success of a P3O?

  1. Increased success of programmes delivering to budget
  2. Improved portfolio balance in relation to spend on short term contract resource
  3. Increased use of implemented tools by operations staff
  4. Enhanced contribution measured against the Benefits Realization Plan

Answer(s): C



Which is an Information Assurance concept that ensures a P3O can supply information to the business when needed?

  1. Asset management
  2. Configuration management
  3. Availability
  4. Confidentiality

Answer(s): C



Which defines what a P3O provides?

  1. Decision-ma king forum for Programme and Project Managers
  2. Decision-enabling model for the entire organization.
  3. Integration with governance arrangements and other corporate support functions
  4. Replacement for Programme and Project Boards

Answer(s): C



Which role has the authority to champion the setup of a P3O set-up?

  1. Head of Programme Office
  2. Head of P3O
  3. Portfolio Analyst
  4. P3O Sponsor

Answer(s): D