A temporary endeavor undertaken to create a unique product or service is called:
Answer(s): A
The process of coordinating the organization, planning, scheduling, controlling, monitoring and evaluating of activities so that the objectives of a project are met is known as:
Answer(s): C
According to Project Management Institute, which of the following is NOT the process group of project?
Answer(s): B
Contract statement of work is the output of which process group?