A process of determining the small minority of a population that accounts for the majority of given effect is called:

  1. Pareto analysis
  2. Statistical analysis
  3. Population analysis
  4. None of the above

Answer(s): A



Downtime during testing, losses in productivity, resistance to change and new manuals are all description of:

  1. Project participants
  2. Logical assets
  3. External suppliers
  4. Internal organization

Answer(s): D



According to Jason Westland, author of Project management Life Cycle, a business case should NOT include which of the following?

  1. a description of the problem under consideration
  2. options available to solve the problem
  3. benefits, costs, risks and feasibility for each available option
  4. post-recommended solution

Answer(s): D



What provides an illustration of the project's scope sand all tasks become the basic for monitoring the project's progress?

  1. Work breakdown structure
  2. Progress structure
  3. Project manual structure
  4. Process flow structure

Answer(s): A