A. Gantt chart
B. Agreement chart C.
Progression chart D.
performance chart

Answer(s): A

QUESTION: 19
A form of network diagram that graphically portray the sequential relationships and
interdependence between the project tasks is called:

A. Steps Forward Method
B. Critical Path Method
C. Evolutionary Method
D. Development Method

Answer(s): B


QUESTION: 20

Coding activities might include:

A. Direct responsibility
B. needs notification
C. issues approval
D. Al of the above

Answer(s): D

QUESTION: 21
A solicitation document used to obtain price quotes for a specified product or service is known
as:

A. Cost summons
B. Invitation for bid C.
Temptation for bid D.
Price Provocation

Answer(s): B

QUESTION: 22
Which of the following is NOT the type of statement of work (SOW)?

A. Project SOW
B. Design SOW
C. Level of effort SOW
D. Performance SOW