Free CPSM1 Braindumps


Answer(s): B

QUESTION: 23
Which of the following are the steps to proposal solicitation?

A. Origination, qualification and Projection
B. Selection, qualification and Management
C. Cooperation, Foundation and negotiation
D. Origination, qualification and negotiation

Answer(s): D

QUESTION: 24
Supply management is involved in projects at the planning stage through source solicitation
planning and selection.

A. True
B. False

Answer(s): A

QUESTION: 25
Which of the following is NOT the type of budget that the supply management budget includes?

A. Purchased materials
B. Capital budget
C. Expense budget
D. Maintenance budget

Answer(s): C

QUESTION: 26
The time that elapses from placement of an order until receipt of the order is called:

A. Lead time
B. Fol ow up time
C. Control time
D. Central time

Answer(s): A

QUESTION: 27
The demand forecast for all products and services then is used to create a , which breaks down
all labor and material requirements, usually by quarter.

https://xcerts.com

Get The Premium Version

Allbraindumps.com
 Test Questions PDF from Myitguides.com

 Test Questions PDF from Myitguides.com