Conflict should be best addressed in which manner?

  1. Early, in private, using a direct, collaborative approach
  2. Early, in public, using an indirect, collaborative approach
  3. Early, in private, using an indirect, cooperative approach
  4. As late as possible, in public, using a direct, confrontational approach

Answer(s): A



The project management processes presented in the PMBOK Guide® should:

  1. always be applied uniformly.
  2. be selected as appropriate by the sponsor.
  3. be selected as appropriate by the project team.
  4. be applied based on ISO guidelines.

Answer(s): C



Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

  1. Fixed Price with Economic Price Adjustments Contract (FP-EPA)
  2. Cost-Reimbursable Contract (CR)
  3. Firm-Fixed -Price Contract (FFP)
  4. Fixed-Price-Incentive-Fee Contract (FPIF)

Answer(s): C



Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

  1. Crashing
  2. Fast tracking
  3. Leads and lags adjustment
  4. Parallel task development

Answer(s): B



What is the definition of Direct and Manage Project Execution?

  1. Integrating all planned activities
  2. Performing the activities included in the plan
  3. Developing and maintaining the plan
  4. Execution of deliverables

Answer(s): B



Viewing page 60 of 112
Viewing questions 296 - 300 out of 704 questions