Situations where standardized work needs to be incorporated include all of these except ________.

  1. Machines continually operating to reduce the labor cost per piece
  2. Lack of a system to assure proper inventory levels at repair stations
  3. Changeover instructions incomplete
  4. Process flow for the same product assembly taking various cycle time for completion

Answer(s): A



The Lean toolbox includes all of these items except ____________.

  1. Mistake Proofing
  2. Visual Factory
  3. Design of Experiments
  4. Inventory Management

Answer(s): C



Questions that can be best answered by a Visual Factory include all of these except _____________.

  1. Are downtime issues easily noted?
  2. Can extra inventory be seen easily?
  3. Are unneeded tools or supplies easily noted?
  4. Are setups optimized for lower scrap levels?

Answer(s): D



If a Six Sigma project was to reduce repair station inventory and the team found the inventory was creeping up over time which Lean tools should be considered in the Control Phase to reestablish and sustain the project success?

  1. Review the Visual Factory to assure inventory in excess of desired visible
  2. Improve the lighting to assure adequate visibility
  3. Analyze data from supplier deliveries
  4. Reword the standardized work instructions to use active verbs and not passive phrases

Answer(s): A



Kaizens or Kaikakus and Six Sigma projects are intended to create incremental process improvements versus breakthrough, significant improvements.

  1. True
  2. False

Answer(s): B